Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 577

A project manager is managing a project to deploy new software to 200 end users. During the implementation, there is a missed process that

caused some of the users to lose their computer data.

What should the project manager do first?

A.

Meet with the team to discuss the root cause and encourage the team to take note of it and continue to focus on the deployment.

B.

Record this case until the final lessons learned session is complete to prevent impacting the team's morale during implementation.

C.

Meet with the team members and request they conduct a review of the case by providing feedback as lessons learned.

D.

Invite a consultant to review the process in order not to repeat the same issue and share the results with the team.

Full Access
Question # 578

A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the

scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively,

among other critical blockers.

What should the project manager do?

A.

Request an additional resource to assist in solving all of the impediments listed by the team.

B.

Determine and agree when a situation becomes an impediment to be solved by the scrum master.

C.

Request the team review and prioritize the open impediments to resolve all of them as soon as possible.

D.

Push back, explaining that a self-organized team should address all of the problems to get the work done.

Full Access
Question # 579

A project manager with global teams is managing a project that is progressing as expected. However, recently the project manager has learned of some team members missing the daily meetings. After investigating the issue, the project manager realizes different time zones is the main cause of the issue.

What should the project manager do next?

A.

Schedule a team-building workshop involving all teams to support better communication.

B.

Schedule a meeting and ask all teams to sort the issues and move ahead with full participation.

C.

Ask everyone to only invite team members in different parts of the world as necessary.

D.

Share the time-overlap schedule with the team to make meeting scheduling convenient.

Full Access
Question # 580

A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,

the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.

What should the project manager have done to prevent this from happening?

A.

Reviewed the acceptance criteria and obtained client approval.

B.

Allocated a risk budget for any post-release improvements.

C.

Conducted a pilot to understand the client's performance parameters.

D.

Established meetings with the client throughout the project phases.

Full Access
Question # 581

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

A.

Execute the smaller estimated activities.

B.

Resize the story points.

C.

Negotiate the estimation so it gets smaller.

D.

Break down the larger activities into smaller ones.

Full Access
Question # 582

A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.

What should the project manager have done to prevent this from happening?

A.

Defined acceptance criteria in a quality checklist agreed upon before starting the build phase

B.

Approved a detailed change management process before starting the build phase

C.

Provided compensation for issues due to the variance in the agreed-upon requirements

D.

Continuously communicated the changes in the work plan and the agreement to the client

Full Access
Question # 583

A company just started managing a project using an agile approach Due to this change, the general manager is worried about the scope definition process for upcoming projects What should the project manager do to ensure the project scope is completely defined?

A.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

B.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk

C.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

D.

Ask the general manager to review every requirement to ensure an projects will deliver the requested products

Full Access
Question # 584

A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule.

What should the project manager do next?

A.

Validate the information and update the risk management plan.

B.

Update the risk register and discuss it with the project stakeholders. b

C.

Source second-hand equipment in order to prepare for any delivery delays.

D.

Update the sponsor of the potential issue and ask for any suggestions.

Full Access
Go to page: