Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 601

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?

A.

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.

B.

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.

C.

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,

D.

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.

Full Access
Question # 602

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?

A.

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values

B.

Send a standard email to the team prior to every daily standup containing the new values

C.

Organize a team meeting focusing on the new values associated with the transformation

D.

Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives

Full Access
Question # 603

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

A.

Reject the risk because the team is not in agreement on escalating it

B.

Include the risk in the risk assessment and evaluate it with the team

C.

Accept the risk and immediately enter the risk into the risk register

D.

Discuss with the consultant to understand why the risk was escalated

Full Access
Question # 604

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget

B.

Engaged with the project sponsor to ensure support for the project manager's decision

C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped

D.

Convinced the functional manager to stop the activities that will run beyond the budget

Full Access
Question # 605

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project's change control board (CCB),

Full Access
Question # 606

A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to

take action in advance to ensure the project succeeds.

What should the project manager do?

A.

Evaluate the project risk and add external experts to address the potential risks.

B.

Inform the project sponsor about the risk and try to convince them to withdraw from the project.

C.

Continue executing the project as planned and add more resources if they are required.

D.

Review the lessons learned on similar projects so that they do not fall back into the same pattern.

Full Access
Question # 607

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

A.

Create an issue log template that will be used to identify and track impediments.

B.

Create a contingency plan in case the project deviates from the initial plan.

C.

Create a schedule management plan to ensure the project meets the delivery date.

D.

Create an assumption log and map assumptions to impediments based on the impact tothe project value.

Full Access
Question # 608

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

A.

Revise the project schedule and inform the stakeholders regarding any delays

B.

Revise the project estimates and meet with the project team to discuss delays

C.

Review the management reserve to identify any costs associated with the delays

D.

Review the contingency reserve to identify any delays to the project

Full Access
Go to page: