Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 593

A project is in the execution phase and there are disagreements between two key stakeholders about the project's scope. One stakeholder is adamant about expanding the scope and the other stakeholder is content with the current arrangement.

What should the project manager do?

A.

Escalate the stakeholder's conflict to senior management so they can resolve the issue.

B.

Schedule a one-on-one discussion with each stakeholder to understand their concerns.

C.

Schedule a meeting with both stakeholders to encourage dialogue and reach a decision.

D.

Suggest that the two stakeholders meet together to agree upon a project scope.

Full Access
Question # 594

A new sales software development project is underway The customer is still finalizing the requirements for the system when a new CEO is introduced. The new CEO is expected to make changes to the organization, which most likely will impact development. However, the most important criterion for the project is that the software must provide correct sales results. No intermediate results are required.

Which project approach should the project manager take?

A.

Incremental

B.

Predictive

C.

Hybrid

D.

iterative

Full Access
Question # 595

A project is 20% complete. The client has accepted a project order amendment that involves a major change. Without this major change, the project result will be useless for the client organization.

What should the project manager do?

A.

Update the project status from "active" to "on hold" until there is more clarity on the scope of the change.

B.

Initiate planning for the project with the modified scope as laid out in the client's purchase order.

C.

Set up a meeting with the client and the project team to identify ways to safeguard the project from the change.

D.

Consult the project sponsor to understand if the change must be processed for project execution.

Full Access
Question # 596

Drag the technical practices on the left to the scenario on the right.

Full Access
Go to page: