Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 553

A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member's performance was poor, and the team had difficulty meeting the iteration goals.

How should the project manager handle this situation?

A.

Inform the human resource (HR) department about the issue.

B.

Allow the project team to discuss the problem with this team member.

C.

Discuss the issue with the team member's functional manager.

D.

Speak to the team member regarding the need to improve performance.

Full Access
Question # 554

A few developers have identified a list of impediments at the daily standup and are asking for the project lead's assistance in prioritizing them. There are a few complex backlog items, and a new junior tester has identified a few compliance defects. The product owner and a couple of developers will be leaving the project team, and the contract with the test and production support partner will not be renewed.

Which issue should the project lead focus on first?

A.

Developing a new contract for production support.

B.

Finding a new product owner to prioritize the product backlog.

C.

Regulatory compliance issues discussed in the meeting.

D.

Recruiting, onboarding, and training new developers.

Full Access
Question # 555

The team's velocity is inconsistent, leading the product owner to believe the team is creating too many points in their user stories.

What should the scrum master do first?

A.

Remind the product owner that their role is to determine what the team should work on during the iteration.

B.

Meet with the product owner for planning and to resize the stories in the backlog.

C.

Invite the product owner to planning poker meetings and get their approval after each story is sized.

D.

Raise this concern with the team and review the performance of the past three sprints.

Full Access
Question # 556

A project manager is overseeing a 10-mile piping installation project that was supposed to spend US$15,000 per mile of piping installation and should complete the project exactly 20 weeks from its start. The project manager just found out that only 80% of the work has been completed.

What is the budget at completion (BAC)?

A.

US$100,000

B.

US$150,000

C.

US$300,000

D.

US$250,000

Full Access
Question # 557

During a planning session, the development team and the product owner are arguing about the effort needed to deliver a specific feature in a software development project. The product owner says that the feature can be developed in one week, whereas the team estimates that it will take at least two weeks. After several hours of discussion, they have not reached an agreement.

What should the project lead do?

A.

Communicate to the stakeholders that the project has to be delayed for two weeks.

B.

Ask the project team to accept the shorter estimate as it is important to keep a good relationship with the product owner.

C.

Decide what should be the time estimate and proceed with the planning meeting.

D.

Educate the product owner that the project team members are the most appropriate group for assessing the effort.

Full Access
Question # 558

While monitoring a project at a work site, the project manager notices that the site team’s work breaks have increased by a few minutes every week. How should the project

manager approach this?

A.

Reduce payment to the workers due to their extended breaks.

B.

Issue a formal written warning to all hourly workers for their break tardiness.

C.

Have a meeting with the team to discuss the issue and propose solutions.

D.

Dismiss some of the workers for failing to adhere to the break policy.

Full Access
Question # 559

In order to increase a project's profit margin, the project manager and subject matter experts (SMEs) agreed to select the oldest model of a

specific machine available in the market. When the machine reached its destination country, it was blocked by customs authorities who restricted

the import of this machine model.

What should the project manager have done to prevent this from happening?

A.

Ensured that the SMEs correctly defined the project scope and the machine model.

B.

Ensured the project sponsor provided enough funding to purchase the latest version of the machine.

C.

Ensured that regulatory compliance was considered in the quality management plan.

D.

Ensured that the technical team researched and selected the latest model of the machine.

Full Access
Question # 560

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.

What should the project manager use to explain the project scope?

A.

Product roadmap

B.

User stories

C.

Business requirements document

D.

Product backlog

Full Access
Go to page: