Question # 537

A project was recently flagged as being noncompliant during an inspection. Several options were suggested on how to address the noncompliance, but each may have different impacts on the budget, schedule, and quality.

How should the project manager proceed?

A.

Review the risk register.

B.

Perform a cost-benefit analysis.

C.

Determine the cost of change.

D.

Conduct a root cause analysis (RCA).

Full Access
Question # 538

During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to

be involved in the regular project communications and reporting cycles.

What should the project manager do?

A.

Ask the project team members to include the manager in all of their communications regarding this project.

B.

Inform the manager that only stakeholders identified in the communications management plan should be involved.

C.

Perform a stakeholder analysis and update the communications management plan to reflect the new situation.

D.

Suggest the manager contact the steering committee and project management office (PMO) to be included.

Full Access
Question # 539

A feature has been added to the iteration backlog that has been prioritized by the project sponsor over other critical security patches. What should the project manager do?

A.

Perform a risk analysis and then meet with the project sponsor to discuss it.

B.

Meet with the project sponsor to discuss the feature with the product owner.

C.

Push back on the feature because it is not an immediate priority.

D.

Give all the work packages parallel priority and continue activities.

Full Access
Question # 540

A project manager is in the process of authoring the communications management plan for a new project. One of the project's stakeholders has a habit of posting work updates on social media, which may include confidential project status updates.

What should the project manager do?

A.

Ensure that social media posts related to the project are removed.

B.

Ensure that sensitive information is not included in stakeholder updates.

C.

Review social media access and restrict it to ensure confidentiality.

D.

Review the protocols and security measures to ensure confidentiality.

Full Access
Question # 541

A Scrum team has information radiators but must also keep stakeholders aware of their progress. In addition, the project management office (PMO) has specific templates for status reporting to management. The project lead realizes that a variety of reporting will be needed to satisfy enterprise and stakeholder needs.

What should the project lead do?

A.

Determine the minimum communications needed for the project, and adapt the communication plans as needed.

B.

Document only the plan for written communications, and send meeting invites for verbal communication sessions.

C.

Follow the project management office (PMO) guidelines for communications instead of generating a project communications management plan.

D.

Create a communications management plan informing all project team members and stakeholders who will receive what type of communication.

Full Access
Question # 542

The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.

Which document should the project manager use to resolve this situation?

A.

Requirements traceability matrix

B.

Risk management plan

C.

Project scope statement

D.

Requirements management plan

Full Access
Question # 543

A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version

is not clear to the stakeholders.

What should the project manager do to increase value delivery?

A.

Use spikes to dig deeper into the technical challenges of the new product, thus reducing the technical risk.

B.

Create a visual task board with all of the relevant stakeholders to support backlog prioritization.

C.

Work with the team on the definition of a minimum viable product (MVP) and present it to the stakeholders.

D.

Gather the team to create a comprehensive product roadmap but only commit to requirements for the next quarter.

Full Access
Question # 544

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

A.

Add more items to the sprint backlog that will add value.

B.

Complete the sprint and seek a waiver from the regulator.

C.

Complete the sprint, but do not release the deliverable.

D.

Perform a sprint risk assessment and analyze challenges.