Question # 545

While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers. What should the project manager do?

A.

Discuss this with the functional manager and related parties.

B.

Reject the functional manager's change request immediately.

C.

Analyze the impact of the change request on the project.

D.

Apply for a formal change control board (CCB) approval.

Full Access
Question # 546

A project manager is working as a servant leader for a pilot project to adopt agile practices. After three sprints, the team demos the product to the

main stakeholders, but receives negative feedback about the product's features. The team feels that all the features met the acceptance criteria

defined by the product owner and does not understand what went wrong.

How should the project manager mitigate the product rejection?

A.

Share the product backlog for the main stakeholders to review in advance.

B.

Engage the main stakeholders in the upcoming sprint review sessions.

C.

Create dedicated sprints to implement feature fixes for the rejected ones.

D.

Ask the project sponsor to evaluate the assignment of a new product owner.

Full Access
Question # 547

A project manager is assigned to a yearlong project. Before the start of the design phase, a competitor announces that they will release a similar deliverable in 8 months, although with fewer features and functionality.

Which two actions should the project manager take next? (Choose 2)

A.

Modify the project management plan with an incremental approach.

B.

Evaluate the impact of incremental deliverables.

C.

Reduce the scope items of the final deliverable.

D.

Discuss and review this external risk with the project sponsor.

E.

Update the project artifacts to include this issue.

Full Access
Question # 548

A project to construct an electricity generation plant is on site near a nature reserve. An environmental activist group is questioning the need for

the project. The customer has informed the project manager to disregard the group as they are not in support of the project.

What should the project manager do next?

A.

Ask the customer to contact the activist group and let them know the project status and completion date.

B.

Add the activist group to the list of stakeholders and analyze the impact they may have on project delivery.

C.

Obey the directive from the customer since they are funding the project and are the most important stakeholder.

D.

Request the project team disregard all communication from the activist group and continue with their project work.

Full Access
Question # 549

A team member on an important company project mistakenly caused significant cost overruns. The sponsor informed the project manager and expects the project manager to take action within 1 week. This team member has always been an outstanding performer.

What should the project manager do first to address the sponsor's concerns?

A.

Document the team member's mistake in the lessons learned.

B.

Train the team member to improve their performance to avoid future mistakes.

C.

Talk with the team member to identify the reason for the mistake.

D.

Relocate the team member to another project due to the mistake.

Full Access
Question # 550

A project manager is managing a project in a fast-paced environment. The project manager needs to empower the team to collaborate toward an expected outcome and enable high-team performance. The CEO has suggested that the project manager apply a servant leadership style.

What should the project manager do to demonstrate the capabilities of a servant leader?

A.

Encourage all team members to develop the perfect plan to achieve the desired results.

B.

Create an environment where all team members compete to achieve the desired results.

C.

Assess the business case and define the project priorities to motivate all team members.

D.

Define the project's objectives and create an environment where all team members can succeed in achieving them.

Full Access
Question # 551

A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.

What should the project manager have done to avoid this setback?

A.

Assessed feasibility and impacts

B.

Developed benchmarking

C.

Analyzed stakeholders

D.

Detailed the project charter

Full Access
Question # 552

A project team has two members with conflicting personalities. This is affecting the rest of the team's performance.

What should the project manager do?

A.

Understand the viewpoint of each team member.

B.

Organize a team-building activity for the team.

C.

Conduct an analysis to measure missed targets.

D.

Seek a solution during the daily coordination meeting.

Full Access