Summer Certification Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 4

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager ' s former department has not completed a task This is delaying the current iteration.

What should the project manager do?

A.

Create an entry in the impediment board and assign it.

B.

Invite the project team to a swarming session to define a solution

C.

Leverage the network of the former department and ask for help

D.

Escalate the issue to the product owner to define the next steps

Full Access
Question # 5

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

A.

Evaluate the impact to the users and create a plan to address it.

B.

Inform users about the new changes and ask for their collaboration.

C.

Ask all managers to collaborate implementing this change to users.

D.

Start implementing the change so that users will eventually get used to it.

Full Access
Question # 6

A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?

A.

Follow the change management process and work with procurement if needed

B.

Engage an arbitrator to resolve any conflict while handling the new requirement

C.

Add the change to the next sprint to meet the customer ' s needs

D.

Allocate resources to work on the new feature immediately to complete the request

Full Access
Question # 7

During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?

A.

Refine and estimate the enhancement so the size is known.

B.

Add it to the product backlog to be completed in the future.

C.

Start working on the enhancement for the customer immediately.

D.

Ask the product owner to prioritize the item with the customer.

Full Access
Question # 8

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

A.

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.

Create a dedicated sprint to complete all of the pending specifications from previous sprints.

Full Access
Go to page: