Labour Day Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2023 Version)

Question # 4

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined,

including a sample machine, and the user interface software that has only a basic specification and a requirement for a user experience design approach.

Which project management approach should the project manager use?

A.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

B.

The software development has a high uncertainty level, so an agile approach is recommended for the project.

C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

Full Access
Question # 5

During the execution of a project, a key stakeholder complains to the project manager about recent communications. The key stakeholder explains that the relevant

information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.

What should the project manager do?

A.

Send relevant information to all key stakeholders simultaneously to ensure consistent communication.

B.

Update the communications management plan to fulfill the key stakeholder's expectations about relevant information.

C.

Explain to the key stakeholder the way in which the project team communicates information.

D.

Ask the project sponsor to hold a meeting with the key stakeholder to ensure that the stakeholder is engaged in the project.

Full Access
Question # 6

Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates

managing resources on projects.

How should a project manager solve this issue?

A.

Promote adoption of the communications management plan with the project team.

B.

Request a meeting with senior management to escalate the situation.

C.

Host a team-building event to develop team cohesion and improve communication.

D.

Propose implementing a new project management information system (PMIS).

Full Access
Question # 7

At a daily standup on the second day of the sprint, the product owner asks one of the developers to add more functionality to a product backlog item that was committed to in the sprint planning. The product

owner explains that the change is based on a discussion they had with a user, is critical, and should be delivered in the next release.

What should the project manager do?

A.

Organize a workshop after the standup to assess the impact.

B.

Prepare a budget change request for additional resources.

C.

Create a new product backlog item for the next sprint planning.

D.

Ask the product owner to provide more details in the standup.

Full Access
Question # 8

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter. The customer wants to show their stakeholders a tangible outcome in

the first quarter and wants to move the second milestone to the first quarter. The project manager explains to the customer that it is not feasible unless the requirements for

the second milestone are changed.

Which two actions should the project manager take? (Choose 2)

A.

Ask the customer for their priorities regarding the requirements for the second milestone.

B.

Convince the customer to leave the second milestone in place and not change it.

C.

Tell the customer that moving the milestone has a very high impact on the cost of the project.

D.

Go back to the development team and discuss which second milestone requirements can be performed in the first quarter.

E.

Escalate the issue to upper management to resolve the problem, and suggest a plan.

Full Access
Question # 9

A project manager has noticed that the performance of a new team member has increased dramatically over the past fewmonths. The project manager hasbeen measuring this team member's performance through the cost performance index (CPI) and schedule performance index (SPI) of work packages. The

project manager has also assigned new, unrelated work packages to this team member. The project manager wants to formally record the team member'ssuccess in the project documentation.

What should the project manager do?

A.

Attach a note to the project management plan about the team member.

B.

Send a communication to management recognizing the team member's contributions.

C.

Hold a project team meeting about the team member's contribution and take minutes.

D.

Record the team member's contribution in the responsibility assignment matrix (RAM).

Full Access
Question # 10

A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to allstakeholders; however, the last department to migrate indicated that they have not received the notification.

What should the project manager do?

A.

Report the issue during the next status meeting at the end of the week.

B.

Escalate the issue to the project sponsor and upper management.

C.

Close out the project and tell the manager to open a service desk ticket.

D.

Log the issue and assign it to the project team member(s).

Full Access
Question # 11

In an agile team, some of the team members are coming forward to ask for more autonomy on the project. What shouldthe project manager do in thissituation?

A.

Discourage this request, as it is for the management team.

B.

Encourage the team lead to make decisions.

C.

Discourage them as conflicts may be created.

D.

Encourage the team members to make decisions.

Full Access
Question # 12

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the

project.

What should the project manager do?

A.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue.

B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain.

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

Full Access
Question # 13

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the

project vulnerable.

What should the project manager do?

A.

Ask human resources (HR) to counsel the team member to balance the workload.

B.

Assess a mechanism for knowledge transfer among the team members.

C.

Ensure the activities of this team member are distributed across the project team.

D.

Motivate the team member to stay by providing them with incentives.

Full Access
Question # 14

An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete thejob successfully. What shouldthe project manager do to reduce the risk of project failure?

A.

Ask the sponsor to add experienced professionals to the team.

B.

Approve the appropriate training program for team members.

C.

Provide team members with the necessary coaching and mentoring.

D.

Assign a dedicated resource to check the quality of each deliverable.

Full Access
Question # 15

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

A.

Ask the team to accelerate the iterations and avoid interruptions.

B.

Verify team performance and ask for improvement during daily standup meetings.

C.

Recommend that the project sponsor increases the budget to bring new resources.

D.

Discuss the problem with the team and decide how to do the work together.

Full Access
Question # 16

A client has requested that a product be implemented in 4 months and is ready to increase their budget to do this quickly. The project manager cannot comply with the request with the current resources or

even additional resources. The project manager estimates that 8 to 12 months are needed for the product to go live.

What should the project manager do to address this situation?

A.

Call a meeting with the client so they will understand that 4 months is not enough time to deliver the product.

B.

Motivate the team to work more efficiently and approve overtime in order to meet the client's goal in 4 months.

C.

Discuss with the client alternative approaches to deliver the minimal viable product (MVP) in 4 months and the rest later.

D.

Seek additional resources from the subcontractors and other sources to parallelize the necessary work.

Full Access
Question # 17

A project manager is struggling to figure out the performance of the project teams in an agile environment. For the same scope of work, team A has calculated 100 story

points and team B has calculated 125 story points.

Which team is performing better?

A.

Team B as they have calculated more story points than team A.

B.

The team that completes the most stories selected from the sprint backlog.

C.

The team with the least amount of defects in their deliverables.

D.

Team A as they have calculated fewer story points than team B.

Full Access
Question # 18

A project team is in the planning phase of a product migration project. The project manager schedules a meeting with the project team, telecommunications team, and the department leaders with group productaccounts. The purpose of the meeting is to determine the project timeline based on how much content needs to be transferred to or created in the new system and the processing procedures and time frames.

Who should the project manager also invite to the meeting?

A.

Representative from the service desk team

B.

Representative from the provisioning team

C.

Representative from the network team

D.

Representative from the reimbursement team

Full Access
Question # 19

In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in

conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?

A.

Anticipate, alert, and follow the risk management process.

B.

Detect, track, and follow the issue management process.

C.

Promote, inspire, and follow the stakeholder engagement process.

D.

Discuss, educate, and follow the communications management process.

Full Access
Question # 20

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the

senior managers claim not to know about the deliverable.

What should the project manager do next?

A.

Check if these stakeholders attend regular project meetings.

B.

Meet with these stakeholders to review the project charter.

C.

Review the project charter to validate this claim.

D.

Validate if the project charter changed from the original one.

Full Access
Question # 21

A business transformation project has a four-phase delivery plan. The project team has successfully delivered one phase of the project.To further enhance team performance and empower team members, which two actions should the project manager take? (Choose 2)

A.

Encourage team members to cross-check decisions with the project manager.

B.

Support team members to make decisions in their areas of strength.

C.

Allow team members to make limited decisions.

D.

Vet all of the decisions before execution.

E.

Organize and assign team members to tasks where they have strengths.

Full Access
Question # 22

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a callfrom the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available.

This is going to significantly impact the deliverable.

What should the project manager do?

A.

Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer.

B.

Ask the product owner to stretch the delivery team further to complete the final product in the original timeline.

C.

Request additional funding from the sponsor to obtain a new resource to fill in the gap.

D.

Inform the customer of the impact immediately and prepare for escalation.

Full Access
Question # 23

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.

What should the project manager have done to prevent this?

A.

Requested robust documentation for the component's build.

B.

Outsourced development of the specific component to another team.

C.

Facilitated cross-functional knowledge transfer during the project.

D.

Acquired more than one resource skilled in each component.

Full Access
Question # 24

An agile project is approaching its first release date, and the product will be supported by the operations team. To ensure proper support for the product, what should the project manager do?

A.

Engage an external consultancy to assemble supporting documents and coordinate the knowledge transfer.

B.

Create and prioritize a support manual on the product backlog to ensure adequate knowledge transfer.

C.

Ensure the operations team has representation in the planning and review meetings and that there are support requirements in the backlog.

D.

Propose a workshop with the operations team to outline all requirements of the new software and how to properly support it.

Full Access
Question # 25

An agile coach and technical writer for a globally distributed agile team are in a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree

on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but the agile coach and technical writer feel that is an inconvenient time for

them.

How does the project lead ensure adherence to agile practices?

A.

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach.

B.

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

C.

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.

D.

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

Full Access
Question # 26

A project manager is appointed to manage an infrastructure project that spans across several countries, including different time zones withina subregion. It is likely thatmost of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

A.

Discuss the concerns with the project sponsor and modify the project charter to include more budget for interactions.

B.

Set the ground rules and identify a contingency plan in the risk register.

C.

Plan a communication method and allow the project team members to virtually interact.

D.

Create a social media group platform for the team to create a supportive environment.

Full Access
Question # 27

A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables,which could impact the overallprogress.

What should the project manager do next?

A.

Meet with the stakeholder to understand what is causing the delays.

B.

Facilitate a brainstorming session to find potential workarounds.

C.

Capture this in the issue log and escalate it to the project sponsor.

D.

Discuss the need to influence this stakeholder with the sponsor.

Full Access
Question # 28

A project manager is asked to negotiate between two team members who frequently have misunderstandings in order to reach an agreement that will advance the project. What should the project manager to?

A.

Encourage a positive ongoing relationship between both of the team members.

B.

Coach and mentor the team members to build consensus and to resolve the ongoing conflict.

C.

Organize a team-building event to improve the morale among team members.

D.

Establish common ground through collaboration and understanding the team members’ needs.

Full Access
Question # 29

A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not shared properly among the team.

This has caused delivery delays and, ultimately, the failure to complete the project.

What is the root cause of this issue?

A.

Lack of team member training on documentation planning

B.

Team cohesiveness was lost because team members worked in pairs

C.

Improper assignment of tasks to team member pairings

D.

Incorrect communication techniques applied during implementation

Full Access
Question # 30

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not

be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?

A.

Schedule a meeting with all stakeholders to extend the project deadline.

B.

Review and update the issue log and determine if any alternative components can be offered.

C.

Add an item to the next status review to make stakeholders aware of the vendor issue.

D.

Replace the vendor with a new vendor who can offer the component on time.

Full Access
Question # 31

A compliance strategy was created during the planning phase of a project. During execution, the project manager left the organization and another project manager was assigned to the team.

What should the project manager do first to ensure the project is compliant?

A.

Meet with the project sponsor to discuss their compliance concerns.

B.

Review the organizational process assets (OPAs) for compliance topics.

C.

Meet with the team to discuss compliance concerns.

D.

Review the compliance strategy and version history.

Full Access
Question # 32

A hybrid project is experiencing several issues with both the agile delivery of the product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

A.

Refer to the communications management plan.

B.

Refer to the stakeholder engagement plan.

C.

Set up a conference call for all stakeholders.

D.

Send an email to all stakeholders.

Full Access
Question # 33

A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, butthe information is critical in the current iteration for clarification on how tasks need to be accomplished.

How should the project manager approach this situation?

A.

Educate the customer and have them participate in daily standup meetings. ®

B.

Request that the customer reviews and clarifies feature definitions for the current sprint.

C.

Send a burndown chart of the current sprint to the customer and seek clarifications.

D.

Schedule weekly meetings and product reviews with the customer to clarify requirements.

Full Access
Question # 34

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the

complexity of the work was underestimated.

What should the project manager do?

A.

Update the issue log and escalate it to the project sponsor.

B.

Ask to replace some team members with more experienced ones.

C.

Meet with the team to review internal actions to resolve the situation.

D.

Ask the technical manager to help the team with the issue.

Full Access
Question # 35

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects. The project manager would like to minimize the impact of the

stakeholder's behavior on the development team.

What training should the project manager choose for their team to help with this situation?

A.

Agile training

B.

Emotional intelligence training

C.

Communication training

D.

Negotiation training

Full Access
Question # 36

A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government official who committed to

delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not

support,

What should the project manager do next?

A.

Inform the new project sponsor that the new aspects will not be included in this project.

B.

Meet with the new project sponsor to review the current project scope and the requested changes.

C.

Invite the project sponsor to a briefing with the project team to demonstrate progress and seek further support to meet project-committed deliverables.

D.

Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.

Full Access
Question # 37

A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master'sprogram will coincide with thelast phase of the project.

What should the project manager do?

A.

Ask the team member to inform human resources (HR) about their enrollment in the master's program.

B.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

C.

Suggest the team member postpone their enrollment in the master's program until the project is completed.

D.

Assess the team member's commitment to the master's program and its impact on project performance.

Full Access
Question # 38

On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project managerrealized that some of the keyactivities were scheduled over the holiday periods in the overseas offices.

What shouldthe project manager do next?

A.

Hire additional personnel on a temporary basis to cover the extra workload during the holiday seasons.

B.

Request that the offices in overseas locations work overtime to mitigate schedule slippages.

C.

Update the schedule to reflect the holidays and notify the project sponsor of the delayed completion.

D.

Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage.

Full Access
Question # 39

Aretail chain is evaluating a project to replace payment systems across all its stores in multiple locations. The project does not pass the financial threshold but is alsoexpected to increase marketshare, improve customer services, and retain more customers. The project is planned as a phased implementation, building on learningfromthe retrospectives during each phase.

How should the business increase the value of the project?

A.

Ask the benefits owner to reassess the identified risks that are impacting the outcomes of the financial benefits.

B.

Consult with experts on methods to reduce costs and increase the financial value of the project. ®

C.

Quantify the expected tangible and intangible benefits in the benefits management plan for each phase.

D.

Use a fishbone diagram to find the root cause of the lower financial benefits with the benefits owner.

Full Access
Question # 40

During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery ofcritical tasks. How should the project manager address this situation?

A.

Call for a team meeting to decide if the changes should be included.

B.

Communicate the concerns to the project management office (PMO) during the weekly project reports.

C.

Initiate the change request to modify the scope and adjust the timelines.

D.

Conduct an impact analysis and present the results to the steering committee for approval.

Full Access
Question # 41

According to this burnup chart for the last 7-day sprint, what should the project lead address with the product owner and team?

A.

The team is not meeting the expectations of the product owner.

B.

The product owner should not ask the team to change their sprint commitments.

C.

The teant…the sprint after it has started.

D.

The team should have stopped on day 4 and started a new sprint.

Full Access
Question # 42

A product owner is trying to understand how many of the user stories have been completed within a 2-week sprint. How should the project manager approach this situation?

A.

Invite the product owner to regular standup meetings.

B.

Use retrospectives to deliver the finished products.

C.

Have a face-to-face conversation with the product owner.

D.

Share the burndown chart with the product owner.

Full Access
Question # 43

A project manager learns that the performance of a high-performing project team member is deteriorating. This team member is a key member of the project.

Which action should the project manager take to motivate and enhance the project team member's performance?

A.

Discuss the issue with the team member and work on an agreed option.

B.

Assign the project team member to more challenging tasks.

C.

Mentor the project team member by providing step-by-step guidance.

D.

Recognize the project team member in a leadership forum.

Full Access
Question # 44

The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.

What should the project manager do?

A.

Inform stakeholders about the delay during project updates.

B.

Determine cross-dependencies and plan a spike in the next sprint.

C.

Discover the gaps in the communications management plan and address them accordingly.

D.

Determine the risks and identify a resolution during the retrospective meeting.

Full Access
Question # 45

A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on theproject due to a lack of resources. What should the project manager do next?

A.

Escalate the issue to the sponsor and debrief them about the situation.

B.

Review the risk management plan to identify the response strategy.

C.

Review the milestone list to determine which tasks can be fast-tracked.

D.

Organize a team meeting to discuss the next course of action.

Full Access
Question # 46

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

A.

Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product.

B.

Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.

C.

Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work.

D.

Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.

Full Access
Question # 47

A project manager is working on a global project. One team member is from a different country and is unableto attend project meetings ona regular basis. Because of this, other team members have started questioning the need for the project meeting. This issue is affecting thetime line deliverable and quality parameters.

What should the project manager do to manage the project deliverables?

A.

Define the rules for the project meeting.

B.

Make it mandatory for all members to discuss their work at project meetings.

C.

Define the agenda for the project meeting.

D.

Make it mandatory for all members to attend all project meetings.

Full Access
Question # 48

A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables.How should the project managerrespond?

A.

Implement stricter controls so that project artifact creation is given the utmost importance.

B.

Facilitate the implementation of an automated tool for the team to manage project artifacts.

C.

Advise the team that solely focusing on artifacts will not produce successful project deliverables.

D.

Recognize the team’s efforts for documenting artifacts and motivate them with an incentive mechanism

Full Access
Question # 49

One of the team members is always late to the daily standup meeting. What should the project manager do?

A.

Reinforce the ground rules for standup meetings with the entire team.

B.

Schedule the meeting at the end of the day to accommodate everyone.

C.

Speak with the team member directly to reinforce the ground rules.

D.

Ignore the situation since the team member is accomplishing their deliverables.

Full Access
Question # 50

A project team has identified a risk and wants to accept it as an opportunity to finish a project earlier than planned. The project manager realizes that the sponsor may not accept the risk since the sponsor is

risk averse.

What should the project manager do?

A.

Convince the sponsor that this will cost less, ultimately resulting in more profit for the sponsor.

B.

Explain to the sponsor that this is a nonevent type of risk and it will be fine to accept it.

C.

Conduct a Monte Carlo analysis to determine if the team will complete the project early.

D.

Create a contingency reserve to cover the risk in order to ensure that the risk will be accepted.

Full Access
Question # 51

One team member is complaining about an agreement made during the last meeting. That team member was present at the meeting and participated in thedecisions registered in the meeting minutes.

What should the project manager do next?

A.

Meet with the team member and search for the root cause of their behavior.

B.

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.

C.

Schedule a new meeting to evaluate the agreement and negotiate a new one.

D.

Talk with the team member and explain that once the meeting ended, the agreement must be respected

Full Access
Question # 52

A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the projectkick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overallproject schedule.

What immediate corrective action should the project manager take?

A.

Discuss the issue with the virtual team members and revise the communications management plan.

B.

Escalate this issue to the virtual team members’ supervisors.

C.

Add this issue to the risk management plan and take action if it persists.

D.

Discuss the issue with the project sponsors and add this as an issue in the issue log.

Full Access
Question # 53

Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing

manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months.

What should the project manager do?

A.

Cancel the meeting series until the marketing team provides a solution.

B.

Consult the project team and discuss the key team members’ availability.

C.

Shift those key members and assign them to another project.

D.

Consult the resource management plan and escalate to the sponsor.

Full Access
Question # 54

Team members of a new scrum team are skilled and excited about the project, despite never having worked together before. The project leader requested an offsite team building activity to talk about the project and get familiar with each other, but the activity was not approved by the sponsor who is trying to save money. The project leader believes it is important to hold a team building activity to bring the team together.

What should the project leader do?

A.

Explain the financial constraint and ask each team member to pay their own share for the event.

B.

Use the office facilities and support to organize an interactive event for the team members in-house.

C.

Tell the team that the event will be handled at the end of the project due to current financial constraints.

D.

Bypass the event because the team members’ seniority is enough to engage without further activities.

Full Access
Question # 55

A large project is affecting the neighborhood in which it is located. The neighbors are not satisfied with the project, and their resistance to the project may affect the project

deadline.

What two actions should the project manager take? (Choose two.)

A.

Analyze the situation and find out what is causing the neighborhood's negative attitude.

B.

Ask the customer to extend the project deadline to allow time for conflict resolution.

C.

Ask the mayor of the city to use their authority to stop neighborhood resistance.

D.

Set up a meeting with neighborhood representatives to win their cooperation.

E.

Send letters to the neighbors and ask them kindly not to disturb the project.

Full Access
Question # 56

A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project

manager has received support for the project from several leaders in the region. However, some people from the government want to stop

this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

A.

Stakeholders who have been identified and who have needs and a potential impact on the project.

B.

Stakeholders who are selected by the project sponsor who have a potential impact on the project.

C.

Stakeholders who are supporting the project in order to obtain additional resources.

D.

Stakeholders who disagree with the project so as to proactively manage their expectations.

Full Access
Question # 57

A project manager has been hired to lead a governance consulting project that is in the initial phase. The project manager has been assigned to evaluate the supplier search activity. There are many interested

candidates, including former suppliers and suppliers recommended by the sponsor.

What should the project manager do in this situation?

A.

Evaluate the suppliers based on their experience and skills in similar projects.

B.

Prioritize evaluation of the suppliers recommended by the sponsor.

C.

Evaluate suppliers who have worked successfully with the company before.

D.

Request the contracting area take charge of the supplier evaluation process.

Full Access
Question # 58

The project team has been exposed to a large number of stakeholders who are going to be operating the system with different levels of engagement. For efficiency purposes, what should the project manager

do first to minimize the number of interactions with all stakeholders, while keeping a collaborative spirit?

A.

Host regular meetings with all stakeholders to keep them engaged and get their feedback.

B.

Meet with all of the stakeholders separately, build a relationship with them, and learn about their needs.

C.

Meet with the stakeholders, document their needs, and agree on the pace and channel of communication.

D.

Perform a stakeholder analysis to define the level of engagement of each stakeholder and act accordingly.

Full Access
Question # 59

During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who

is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during

meetings.

How should the project manager handle this moving forward?

A.

Update the project schedule to cater to this particular stakeholder.

B.

Allocate time to gain buy-in from the stakeholder prior to key decision meetings.

C.

Ask that only key decision makers attend the project meetings. O

D.

Update the risk register to consider the possible project impacts.

Full Access
Question # 60

A multicultural team is working on a project. After a few months of observation, the project manager realizes that two teammembers are not responding tothe construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the

construction manager.

What should the project manager do to improve the situation?

A.

Ask the construction manager to meet with the two team members to resolve the situation.

B.

Ask the team members to tolerate the cultural differences as they have a different cultural background.

C.

Discuss the team members’ concern with the construction manager and seek solutions.

D.

Provide the construction manager with instructions on how to resolve the situation.

Full Access
Question # 61

Ateam is not delivering the committed work. Cards are not moving on the kanban board, and the burndown chart shows that the sprint progress is slow.

What should the agile project manager do?

A.

Change the work in progress (WIP) limit to reflect the team's capacity.

B.

Discuss the performance with senior leadership.

C.

Meet with the project team members who are slow in delivering tasks.

D.

Consider the use of alternative performance metrics.

Full Access
Question # 62

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept thisrejection and does not want tocontinue the project without the change.

What should the project manager have done to avoid this situation?

A.

Ensured that the change request was aligned with the project scope.

B.

Requested that the sponsor approved the change request first.

C.

Submitted the change request directly to the CCB.

D.

Assessed the change's overall impact to the project before submission.

Full Access
Question # 63

A client has asked the project manager for the program status report. The project manager sends the report and then realizes that they accidentally included another manager from the client'sorganization onthe email.

What should the project manager do?

A.

Wait for the client's feedback regarding the report.

B.

Resend the email to the client, excluding the other manager.

C.

Inform the client and their supervisor about the mistake.

D.

Contact the other manager and ask them to delete the email.

Full Access
Question # 64

A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.

Full Access
Question # 65

A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.

Which evaluation practice should the project lead use to obtain accurate usage data?

A.

Build the functionality in the software to collect the operational usage data.

B.

Send out a questionnaire to all users regarding the most useful features.

C.

Embed a feedback form into the system for users to respond.

D.

Interview a sampling of users to obtain the usage data.

Full Access
Question # 66

In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.

Match the project manager's goals on the left with the relevant risk parameter on the right.

Full Access
Question # 67

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

A.

Update the stakeholder register.

B.

Consult the project sponsor.

C.

Refer to the resource management plan.

D.

Modify the statement of work (SOW).

Full Access
Question # 68

Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two

members are tense around each other and are taking everything personally.

What should the project manager do?

A.

Send both team members to the human resources (HR) department for an acceptable resolution.

B.

Understand each team member's argument and select the one that results in less risk to the project.

C.

Help the team members to resolve the conflict in a way that results in the best team performance.

D.

Offer a compromise that is acceptable to both team members, even if it may not be the best solution.

Full Access
Question # 69

An agile project team is creating an enterprise workflow system for a company. One of the project team members, who is the system design architect, keeps receiving telephone calls from the users who are

asking questions about the system. The calls are impacting the architect's daily work schedule.

What should the project manager do?

A.

Revise the backlog and assign stories to another team member to reduce the architect's workload.

B.

Include user training materials as part of the project deliverables so that users can receive self-help.

C.

Ask the system architect to write up a self-help manual so that the users can resolve the questions by themselves.

D.

Ask the users to send emails instead of calling so that the system architect can reply when they areavailable.

Full Access
Question # 70

A project manager for an application development firm is meeting with stakeholders prior to the launch of the latest release of the company's most profitable application. The stakeholder mentions the following key points:

• A major corporate rebrand was scheduled to occur with this launch, but the rebrand has been delayed by 3 weeks.

• Development processing improvements will be ready in 4 weeks.

• The company is preselling the updated product with a release date of next week.

Which action should the project manager recommend to the sponsor?

A.

Have the sales team reach out to customers to communicate that the product release is being delayed.

B.

Suspend the release of the product until the marketing delay has been resolved.

C.

Delay the rebranding and release the product now to address the realized improvements and meet the sales commitments

D.

Postpone the product release until the processing improvement delay has been resolved

Full Access
Question # 71

An agile project is running its second iteration out of six. A marketing director, who is a key stakeholder, contacts the project lead for a highlevel report of the project.

What should the project lead do?

A.

Tell the stakeholder that a new report will be produced at the end of the iteration.

B.

Explain to the stakeholder that the key indicators are by iteration.

C.

Ask the product owner to develop the new report based on the iteration information.

D.

Develop the requested report based on the iteration information.

Full Access
Question # 72

A project manager received a request to add features and functions to the project after the scope had already been established. What should the projectmanager do?

A.

Follow the stakeholder engagement process.

B.

Follow the risk management process.

C.

Follow the change management process.

D.

Follow the requirements management process.

Full Access
Question # 73

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

A.

Reject the changes as the lead time is too short.

B.

Determine whether the project team is capable of making the changes.

C.

Review the additional changes and perform integrated change control.

D.

Check if the changes are covered in the statement of work (SOW).

Full Access
Question # 74

A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?

A.

Reject the changes as the project is in the final stages.

B.

Perform a detailed assessment to analyze the impact.

C.

Use schedule compression methods to alter the critical path.

D.

Initiate a risk response strategy from the risk register.

Full Access
Question # 75

A construction company recently won the bid for a project to build a cable bridge. A project charter has been prepared and a project manager has been assigned. The project manager is creating a work breakdown structure (WBS) for the project.

To what level should the project manager decompose their project?

A.

To the level where the highest level of quality is maintained

B.

To the lowest level where cost and duration can be estimated and managed

C.

To level four of the schedule for bridge construction

D.

To the level where the bridge can be constructed safely

Full Access
Question # 76

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to

completing the project execution phase.

What should the project manager do next?

A.

Ignore the new requirements as the current budget and schedule do not allow for any changes.

B.

Proceed with the defined project requirements and delay implementing the new requirements.

C.

Add the new requirements to the project scope immediately since they are mandatory changes.

D.

Review the new requirements with the compliance department to determine if a change request is needed.

Full Access
Question # 77

A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for

installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.

What does the project manager need to do now?

A.

Inform the project team only.

B.

Inform the product owner.

C.

Inform the relevant stakeholders.

D.

Inform the project sponsor.

Full Access
Question # 78

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to apredictive project that is offtrack from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on theproject. The stakeholders are unhappy and ask senior management to replace the project manager.

How should the project manager approach this situation?

A.

Socialize with the stakeholders to better understand their needs and reset expectations.

B.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.

C.

Continue to work on the project until the stakeholders and management come to a decision.

D.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.

Full Access
Question # 79

A project manager prepared a project benefits management plan. Which of the following should be included in this document?

A.

Target benefits, benefits owner, lessons learned

B.

Project requirements, target benefits, issue log, metrics

C.

Target benefits, strategic alignment, time frame for realizing benefits

D.

Strategic alignment, benefits owner, risk register

Full Access
Question # 80

A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.

What should the project manager do?

A.

Assign an owner for each backlog activity and track progress.

B.

Ask for more resources to clear the backlog activities.

C.

Prioritize which backlog activities should be kept.

D.

Work on the backlog activities with fewer story points.

Full Access
Question # 81

A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the differentrequirements?

A.

Include only the key requirements and keep the stakeholders informed about scope decisions.

B.

Add only the opinions of the team, because they know the objectives of the project.

C.

Include only the common requirements of each stakeholder group in the project goals.

D.

Analyze the interests and influence of stakeholders and evaluate their requirements.

Full Access
Question # 82

A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use toupdatethe details and communicate to relevant stakeholders?

A.

Change request

B.

Project schedule

C.

Risk register

D.

Issue log

Full Access
Question # 83

A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.

How should the project manager address this situation?

A.

Ensure the feature's tasks are included in the iteration backlog, explain to the sponsor the consequences of the request, and ask the team to deliver the feature in the current iteration.

B.

Ensure the feature has been included in the product backlog, then hold a meeting with the team and sponsor to determine how to deliver the feature within the current iteration.

C.

Ensure the feature is included in the iteration backlog, ask the team to work on the current tasks first, and include the new tasks after those tasks are completed.

D.

Ensure the feature has been included in the product backlog, explain to the sponsor the consequences of the request, and ask the team to include the features tasks in the next iteration.

Full Access
Question # 84

A project team consists of members based in country A and subject matter experts (SMEs) based in country B with a 12-hour time difference. What can the project manager do to improve interactions between the team members in both countries?

A.

Ensure full participation of both the product owner and business SMEs in scope planning sessions.

B.

Explore the opportunity to have both teams colocated.

C.

Identify virtual communication methods and arrange for regular team meetings accordingly.

D.

Plan for frequent face-to-face meetings.

Full Access
Question # 85

A project delivers every 2 weeks. The customer raises a complaint because they do not perceive business value in the products delivered even though deliveries have been completed in a timely manner.

Which activity should the project manager undertake?

A.

Change the delivery project approach.

B.

Perform a cost-benefit analysis.

C.

Review the risk analysis.

D.

Review the definition for the minimum viable product (MVP).

Full Access
Question # 86

After 35 years of service, a company's CEO has retired. The new CEO is planning to digitally transform the company and has assigned a new project manager to assist in this endeavor. The initial backlog has been created and agreed upon, and the team members have been assigned.

What should the project manager do before the project kick-off meeting?

A.

Conduct a backlog refinement and identify the key activity to start with.

B.

Compare the team's expertise against the project requirements.

C.

Perform integration management activities to consolidate the plans.

D.

Review the project's environment to understand the organizational culture.

Full Access
Question # 87

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user partywas not included in any of therequirements collection communications.

Which of the documents was likely missed or outdated?

A.

Stakeholder Register

B.

Business Documentation

C.

Project Charter

D.

Risk Register

Full Access
Question # 88

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks theproject manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?

A.

Risk to delivery

B.

Technical complexity

C.

Estimation accuracy

D.

Business value

Full Access
Question # 89

A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is

dissatisfied, stating that the deliverables do not meet the quality specifications.

What should the project manager do in this situation?

A.

Notify the stakeholder that arbitration procedures will be followed.

B.

Review the requirements traceability matrix and conduct inspections.

C.

Document the issue in the issue log and send a report to management.

D.

Inform the project sponsor of the stakeholder's dissatisfaction.

Full Access
Question # 90

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the project manager ensure that the needs of stakeholders are consistently met?

A.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

B.

Identify all the critical stakeholders during project initiation.

C.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

D.

Add more iterative techniques to improve stakeholder learning.

Full Access
Question # 91

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

A.

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

Full Access
Question # 92

A project manager has been assigned to an education project with the objective of training a workforce in application development. One ofthe deliverables is to provideinternships to the best students in the customer's active projects. However, the customer does not have enough projects in progress right now. The project manager decidesto create several internal projects in order to ensure the internships.

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose 3)

A.

Influence the client to initiate a new project.

B.

Create a change request with the scope of the new internal projects.

C.

Use the project's contingency budget.

D.

Manage the quality of the delivery.

E.

Create a work breakdown structure (WBS) of the new scope with the internal projects.

Full Access
Question # 93

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. Theproject manager has to meet animportant milestone in a week.

What should the project manager do next?

A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.

B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.

C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.

D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.

Full Access
Question # 94

A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access

to water. What should the project manager do next?

A.

Hire local contractors who are familiar with the environment.

B.

Start project planning and develop the project management plan.

C.

Face the challenge immediately and start sending relief to the town.

D.

Process a change request for additional funding due to project urgency.

Full Access
Question # 95

A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and thestakeholder notices that an important functionality for their area was not tested.

Which tool should the project manager have used to prevent this situation?

A.

Project charter

B.

Stakeholder register

C.

Project scope statement

D.

Issue log

Full Access
Question # 96

A project manager has recently joined a small company. The company's chief operating officer (COQ) asked the team to skip some steps in the process inorder to work more quickly. The project manager wants to ensure that these steps are not skipped in the future.

What should the project manager do?

A.

Escalate the issue to the other executive leadership members.

B.

Notify all team members that all steps in the process must be completed.

C.

Schedule a review of the process steps with the team and the COO.

D.

Redesign the process so the team can move more quickly.

Full Access
Question # 97

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The

licensing cost is significant.

What should the project manager do next?

A.

Escalate the licensing issue to the product owner.

B.

Evaluate the impact of nonrenewal of the license.

C.

Add a spike to the backlog for an alternative design.

D.

Raise a change request to secure the renewal.

Full Access
Question # 98

An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the

intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

A.

Requested an experienced resource as a replacement

B.

Convinced the critical resource to remain on the project

C.

Allocated additional time for mentoring

D.

Negotiated additional time to complete the project

Full Access
Question # 99

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are

reporting that they are unable to find the latest project schedule.

What should the project manager do?

A.

Send the project schedule via email to the stakeholders who need that information.

B.

Make sure all stakeholders have access to the system and know where to find project artifacts.

C.

Escalate the issue to the steering committee and ask them to deal with the stakeholders’ lack of training.

D.

Advise the project management office (PMO) that there is a resource gap for sharing project artifactseffectively.

Full Access
Question # 100

A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.

What should the project manager do next?

A.

Instruct the team to analyze and interpret the data before including it in the report.

B.

Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.

C.

Instruct the team to make only a graphical representation of all the data for the report.

D.

Instruct the team to conduct a meeting with the stakeholders before finalizing the report.

Full Access
Question # 101

A client's company announces a reorganization, which includes changes in the senior management involved in the project. The new project sponsor is asking to put the projecton hold until they review thescope.

What should the project manager do next?

A.

Discuss the requirements and update the project management plan with the new sponsor.

B.

Discuss the issue with the project team and update the project management plan.

C.

Amend the risk register and provide suggested mitigation strategies.

D.

Wait for a new project scope from the new project sponsor.

Full Access
Question # 102

A project is in the middle of the fifth iteration. Due to a sudden slump in the economy, the company recorded a drastic reduction in revenue. The strategic direction was to implement cost-reduction measuresimmediately.

What should the project manager do next?

A.

Schedule a meeting with the product owner, discuss priorities, and decide if anything from the backlog can be eliminated, based on current constraints.

B.

Continue the current sprint without interruption and address priorities in the upcoming product backlog grooming sessions.

C.

Allow the project team to decide on the best path forward for the current sprint. ~ J

D.

Meet with the sponsor for guidance on the best path forward before executing sprints.

Full Access
Question # 103

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeksdue to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

A.

Convince the team member not to leave until the project is completed.

B.

Reach out to the procurement team to hire a substitute for the team member.

C.

Allow senior management to decide how to proceed with the project.

D.

Reach an agreement with the team on how to handle the situation.

Full Access
Question # 104

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined.

The actual invoice payments received have also been late and were outside of the contracted payment schedule. Recent invoices have only been partially paid.

What should the project manager do?

A.

Review past projects for payment-related lessons learned.

B.

Conduct a meeting with the project team to update the procurement management plan.

C.

Add nonpayment to the issue log and keep tracking payments.

D.

Hold a meeting with the client to address the issue.

Full Access
Question # 105

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that could becomeunmanageable with time. What should the project manager do?

A.

Compare the cost of improving quality against the cost of failure and adjust the budget.

B.

Help the team create the definition of done (DoD) to improve delivery quality. 0 2 Add testing items to the backlog to assess quality periodically. oO

C.

Expand the team in order to improve the quality of the project.

Full Access
Question # 106

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed.

During a recent external audit, the project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

A.

Ensured that all the required approvals were received per the organizational procedures

B.

Ensured that all defects identified during testing were resolved before implementation

C.

Ensured that all of the required tasks identified in the scope were completed successfully

D.

Ensured that all documentation was completed post implementation before closing the project

Full Access