Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 65

A project manager is working on a complex project with a high degree of change. What strategy should the project manager use to ensure a

successful project completion?

A.

Update the project management plan to reduce the possibility of scope creep.

B.

Schedule a regular risk review with the project management team.

C.

Increase the active engagement and participation of key stakeholders.

D.

Create a project change roadmap to keep track of all unforeseen changes.

Full Access
Question # 66

From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?

A.

Inform the client that extra resources will be added to give the client more time for reviews.

B.

Update the project risk register with the potential for delays

C.

• Work with the client on an acceptable amount of time for document approval

D.

Inform the client of their responsibility in relation to document approval

Full Access
Question # 67

During the release of an important product, a vice president for a different product line brought a valid concern to the project team, which had to be completed before the release. The vice president has not participated in other product discussions until now. This additional work resulted in a delay of the product release.

How should the project manager have handled this situation earlier in the project?

A.

Identified the vice president as a stakeholder

B.

Recorded the vice president's concerns in the risk register

C.

Escalated any dissent to top management right away

D.

Shared project boundaries so that everyone was aware of the scope

Full Access
Question # 68

A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

A.

Ask the sponsor to increase the budget and schedule of the project to accommodate the additional scope.

B.

Encourage the sponsor to start another project for the additional location so that the current project is not impacted.

C.

Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project.

D.

Discuss with the sponsor that the project scope is approved and it is not possible to include two locations as it will affect the budget.

Full Access
Question # 69

A project manager is leading a hybrid project funded by a time and materials (T&M) agreement. The project was completed, and the client

accepted the delivery of the product. One week later, the client asked the project manager to fix two defects they found in the product. The project

manager responded with an estimate of time and money and asked the client to confirm this. The client disagreed and insisted that the work

should be done for free because it is a defect in the product.

What should the project manager have done to prevent this?

A.

Trained client engineers to support the product after its delivery.

B.

Reviewed the project quality control plan with the client.

C.

Suggested a fixed-cost basis and included free bug fixes for 1 month.

D.

Planned how the delivered product will be supported after its delivery.

Full Access
Question # 70

A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.

What should the project manager do next?

A.

Modify the PMO template to include the information.

B.

Contact the senior manager and discuss their needs.

C.

Give the senior manager access to the product backlog.

D.

Organize a review of the kanban board with the manager.

Full Access
Question # 71

A project manager is managing a project to deploy new software to 200 end users. During the implementation, there is a missed process that

caused some of the users to lose their computer data.

What should the project manager do first?

A.

Meet with the team to discuss the root cause and encourage the team to take note of it and continue to focus on the deployment.

B.

Record this case until the final lessons learned session is complete to prevent impacting the team's morale during implementation.

C.

Meet with the team members and request they conduct a review of the case by providing feedback as lessons learned.

D.

Invite a consultant to review the process in order not to repeat the same issue and share the results with the team.

Full Access
Question # 72

A project manager is trying to define a project time line despite having incomplete and ambiguous information on requirements and regulations. What should the project

manager do to finish planning?

A.

Review project documents to identify and eliminate uncertainties and inconsistencies.

B.

Execute a root cause analysis to discover the underlying factors that might lead to risks and issues.

C.

Perform an assumption and constraint analysis to provide more opportunities and remove limiting factors.

D.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

Full Access
Go to page: