Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 49

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid

What should the project manager do?

A.

Add nonpayment to the issue log and keep tracking payments

B.

Hold a meeting with the client to address the issue

C.

Review past projects for payment-related lessons learned

D.

Conduct a meeting with the project team to update the procurement management plan

Full Access
Question # 50

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

A.

Recruit the best resources within the organization to be part of the virtual team

B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.

Identify the types and quantities of resources required for each work package or activity

D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.

Verify if team members are on more than one team and cannot devote enough time to this team

Full Access
Question # 51

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

A.

Mark the product backlog completion status and update the communications management plan.

B.

Ensure that knowledge transfer activities are executed as planned

C.

Release the resources and plan for a project completion celebration.

D.

Hold a steering committee meeting to inform them of the project completion

Full Access
Question # 52

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

A.

Conducted agile training for all employees ranging from the project teams throughmid-level to upper-level management.

B.

Conducted a postmortem and captured the learning in organizational process assets(OPAs) for future use.

C.

Assessed the organization's culture, performed a suitability analysis, and determinedthe future state.

D.

Hired a third-party agile delivery team to do the implementation.

Full Access
Question # 53

For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available

Why is an attendance list important?

A.

It is standard practice on projects to conduct risk review meetings which should have records on meeting attendance

B.

The attendance list is evidence that risk review meetings were held with the appropriate project team members

C.

It is a record that shows the number of attendees in the meeting

D.

It is a document that is registered within the lessons learned register

Full Access
Question # 54

A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.

What should the project manager do next?

A.

Review the latest project management standards with the project management office (PMO) and make changes to the quality management plan.

B.

Perform quality assurance to review the processes against the quality management plan and identify gaps.

C.

Review and update the project document repository with the missing documents and approvals.

D.

Change the quality management processes to align with the project objective.

Full Access
Question # 55

A new agile project manager is trying to determine how the team is performing against the schedule for a release. Which tool will provide a deeper look into the team's progress?

A.

Release plan Sy

B.

Product roadmap

C.

Kanban board

D.

Burndown chart

Full Access
Question # 56

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?

A.

Add a fixed number of change requests allowed by the client on the project baseline.

B.

Request sponsor approval for all change requests to reduce the number of changes.

C.

Initiate the number of iterations to reduce the number of change requests.

D.

Reduce the number of approvers required to implement a change request.

Full Access