Cyber Monday Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 97

A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget

What should the project manager do next?

A.

Request a replacement resource

B.

Perform a cost-benefit analysis

C.

Implement risk responses

D.

Perform Integrated Change Control

Full Access
Question # 98

During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics

1,600 rpm (rate-per-minute) -> stops working and crashes the system

1.500 rpm (rate-per-minute) -> warns of max rate allowed

1.400pm (rate-per-minute) -> reduces the power and brakes the engine

Which of the following statements is correct?

A.

0 1,600 rpm is a project risk,1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project issue.

B.

1,600 rpm is a project issue,1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project risk

C.

1600 rpm is a project issue; 1,500 rpm is a project risk; and1,400 rpm is an event that triggers a response strategy

D.

1.600 rpm is an event that triggers a response strategy.1,500 rpm is a project issue and 1,400 rpm is a project risk.

Full Access
Question # 99

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs

B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team

C.

The project manager should allow the resources to periodically choose on which team they would like to work.

D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization

Full Access
Question # 100

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status

What should the project manager do?

A.

Update the stakeholder engagement assessment matrix

B.

Update the communications management plan to include informal requests

C.

Ask the team member to develop a dashboard to fulfill the request.

D.

Tell the team member to route the request through the project manager

Full Access
Question # 101

A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?

A.

Review the stakeholder register and ensure that communications are being followed in line with the communications management plan.

B.

Isolate the project team from external factors such as senior management and stakeholders so that decisions can be made more quickly

C.

Review the remaining scope and rebaseline the project’s schedule to take into account delays in decision making

D.

Review the adequacy of the project's governance and ensure that an appropriate structure is in place

Full Access
Question # 102

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.

What should the project manager have done to avoid this situation?

A.

Ensured the project repository is up to date.

B.

Updated the job descriptions for all team roles.

C.

Provided specialist training for all team members.

D.

Made an effort to reemploy the senior project team member.

Full Access
Question # 103

An agile project team is building a new product. The stakeholders require ongoing

illustration of project business value.

How should the project manager proceed?

A.

Prepare performance value reports for the business on an ongoing basis.

B.

Include demonstrations of the built portion of the product at the end of every sprint.

C.

Prepare a project report for the stakeholders and distribute it weekly.

D.

Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.

Full Access
Question # 104

A project manager holds meetings every Monday to review the team members' progress. The project sponsor is insisting on daily updates to ensure improved delivery on products developed by all of the teams, including this one. Some learn members indicate they are on a very light time line and would attend me Monday meeting, but not the daily update meetings.

What should the project manager do to ensure all team members participate in daily meetings?

A.

Analyse the team members' influence levels and schedule a training on the importance of daily standups and the time-bound feature of the meetings.

B.

Require all team members to attend the daily review meetings as they ate requested by the project sponsor.

C.

Inform the functional manager and replace (earn members who cannot join the daily progress meetings.

D.

Review the influence of each team member, call the team members with the highest influence to a meeting, and convince them to join the daily standups.

Full Access
Go to page: