Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 81

A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned

cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.

What should the project manager have done to avoid this situation?

A.

Captured and reviewed all of the project work and related costs regularly

B.

Notified all vendors about the invoicing and nonpayment deadlines

C.

Reviewed the total committed cost against the cost invoiced at project closing

D.

Involved the finance team and discussed the issue with the vendor

Full Access
Question # 82

A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.

What should the project manager's first action be?

A.

Indicate that on the new technology is the functional manager's responsibility.

B.

Review the project charter to determine if the training is in scope and, if not, put in a change request.

C.

Consult with the organizational change management specialist as to what the training plan includes.

D.

Document the skill requirements for the product to determine what training is needed.

Full Access
Question # 83

A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.

What should the project manager do?

A.

Discuss with the team the need for longer hours to minimize the impact.

B.

Inform the project team that they may proceed at a more relaxed pace.

C.

Inform the project team that some of them will work for the vendor.

D.

Discuss with the project team alternative options to deliver as planned.

Full Access
Question # 84

A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of

the team members were stressed due to over commitments.

What should the project manager do?

A.

Help the team members by organizing regular stress-relieving and team- building sessions.

B.

Request additional resources to continue delivering value while reducing team stress.

C.

Support the team during the planning phase to only commit to what they are able to deliver.

D.

Ask individual team members to plan staggered leave to avoid becoming stressed.

Full Access
Question # 85

A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted

that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.

What should the project manager have done to avoid this situation?

A.

Allocated a dedicated handover team at early stages of the project

B.

Allocated proper resources for training on BMS in the project plan

C.

Made some adjustments to BMS to be more suitable for the teams

D.

Brought both teams together in a joint meeting to resolve the issue

Full Access
Question # 86

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?

A.

Reduce the priority of project risks as all remaining risks are low-level

B.

Notify stakeholders that all high-level risks have been resolved

C.

Reevaluate identified risks and update the risk register

D.

Reclassify low-level risks as high-level risks

Full Access
Question # 87

During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path

What should the project manager do to avoid future delays?

A.

Submit a change request.

B.

Add additional resources to the project

C.

Update the scope of work.

D.

Review the risk management plan

Full Access
Question # 88

Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.

What should the project manager do?

A.

Reschedule on-site training to online sessions.

B.

Create a risk and assign remediation actions.

C.

Cancel all of the on-site training sessions.

D.

Document the project issue and provide options.

Full Access