Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 377

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

A.

Assess the business value impact and review the product roadmap to include any changes

B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

Full Access
Question # 378

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?

A.

Ask the team to focus on and deliver only the agreed-upon features.

B.

Request additional budget because additional features are being added.

C.

Encourage the team to continue, as this will eventually help the customer.

D.

Ask the product owner to add the additional features to the requirements.

Full Access
Question # 379

we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?

A.

Discuss the issue with the team to resolve the disagreement.

B.

Ensure that there is consensus among the project stakeholders.

C.

Discuss the issue during the next sprint planning meeting.

D.

Support the outcome of the architects’ agreement.

Full Access
Question # 380

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

A.

Update the scope management plan to track the new government requirements.

B.

Accept the cybersecurity team’s request as the security of the company is at risk of

being noncompliant.

C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.

Request a change through the change control process to manage the new cybersecurity

requirements.

Full Access
Question # 381

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

A.

Move the solution designer to another team.

B.

Review the process that resulted in this situation.

C.

Stop work until the design document is completed.

D.

Ask the team to document the design.

Full Access
Question # 382

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Full Access
Question # 383

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.

Use a single communication medium such as video teleconferencing to limit confusion.

C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.

Send frequent updates via email to each stakeholder because this is an information technology project.

Full Access
Question # 384

As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved

How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

Full Access
Go to page: