Halloween Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 353

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area

What should the project manager do first?

A.

Identify an alternative site.

B.

Update the issue log

C.

Issue a change request

D.

Update the risk register.

Full Access
Question # 354

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?

A.

Accept the change and use contingency funds to implement this change with minimal schedule impacts

B.

Reject the change because it is contrary to what was agreed to during earlier phases of the project

C.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps

D.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor

Full Access
Question # 355

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have differentstakeholders than the previous project

Full Access
Question # 356

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

A.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables

B.

Request more funding from the project sponsor to hire additional skilled resourcesand to incorporate additional quality in the project delivery approach and outcome

C.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions

D.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives

Full Access
Question # 357

A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?

A.

Include the issue in the risk register and update the team

B.

Document the continuing issue and failed solution

C.

Inform the stakeholders about the failure and update the issue log

D.

Meet with the project team to find another solution

Full Access
Question # 358

A protect manager is struggling to obtain participation from key stakeholders who do not usually attend project meetings What should the project manager do1?

A.

Distribute the communications management plan

B.

Reschedule meetings lo align with the stakeholders' availability

C.

Escalate the issue to senior management

D.

Set clear meeting expectations by sharing agendas in advance

Full Access
Question # 359

A project manager has been asked to participate in the procurement process for a

software application that allows customers to buy online e-learning courses. The project

manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

A.

Ensure that the requirements for the project are understood and that the objectivesare verified before approval of an agreement.

B.

Inform the project sponsor that once the agreement has been signed, there cannotbe any changes to the scope of the project.

C.

Notify the project sponsor that the project manager cannot be involved in theagreement negotiation process.

D.

Ask the project sponsor to involve the legal department in the negotiation for the project agreement.

Full Access
Question # 360

During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?

A.

Add the stakeholder details into the periodic reports and update the project management plan

B.

Invite the stakeholder to all future project review meetings and update the project management plan

C.

Update the project management plan with the new information and inform all of the relevant stakeholders

D.

Meet with the stakeholder to better understand their expectations and update the stakeholder engagement plan

Full Access
Go to page: