Halloween Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 345

The project team members have finalized the technical specifications after their discussion with the machine manufacturers. However, it has been identified that the specifications are not aligned with the project management office (PMO). The project team members are confident about their choice of specifications.

What should the project manager do in this situation?

A.

Request a decision from the project sponsor.

B.

Give approval of the technical specifications.

C.

Ask the sponsor for additional funding to hire a senior subject matter expert (SME).

D.

Schedule a meeting with all of the subject matter experts (SMEs) to discuss.

Full Access
Question # 346

A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.

What should the project manager do?

A.

Investigate alternatives for team member needs.

B.

Evaluate the engagement needs for stakeholders.

C.

Identify the root cause of the team member's misunderstanding.

D.

Build trust and influence stakeholders.

Full Access
Question # 347

A project manager notices during project meetings that some team members repeatedly threaten to resign when they do not agree with something. Which phase of conflict escalation is the project in?

A.

Beginning

B.

Resolution

C.

Intensification

D.

Final

Full Access
Question # 348

A project manager has been assigned to a new project. The project sponsor has requested a detailed time line, but the project includes some deliverables that are not yet clearly defined.

Which project management approach should the project manager advise using?

A.

As the project includes elements that are not yet clearly defined, an agile approach is the best option.

B.

As the project sponsor has requested a detailed time line up front, an agile approach is the best option.

C.

As the project appears to have both agile and predictive elements, a hybrid approach is the best option.

D.

As the project includes elements that are not yet clearly defined, a predictive approach is the best option.

Full Access
Question # 349

A project manager is approached by two new product owners who were instructed by their managers to join a new agile team. Both product owners were told they could start working with the new agile team immediately.

What should the project manager do to advise both product owners?

A.

Modify the communications management plan to integrate the new product owners into the teams effectively.

B.

Reiterate that having one product owner will improve clarity and accountability.

C.

Present the product owners' product backlogs and prioritize the team's assigned requirements.

D.

Confirm that two product owners are necessary and that both will report to an overarching chief product owner.

Full Access
Question # 350

During the initiation stage of a multimedia exhibition-design project the project manager is developing the project management plan What should the project manager do to complete this task?

A.

Benchmark other similar exhibitions' deliverable lists and final outcomes

B.

Initiate a survey to solicit end-customer opinions and prioritize exhibition contents

C.

Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list.

D.

Initiate an additional services agreement in case the key deliverables list was not clearly stated in the contract

Full Access
Question # 351

A company's project management office (PMO) has started to implement iterative tools A project manager is starting a new project and has identified an opportunity to use the iterative tools One of the senior managers is concerned about this modified framework as it is fairly new to the company

What should the project manager do first?

A.

Organize individual sessions with the stakeholders to build awareness and trust in the new framework

B.

Look for external training on the new framework to eliminate the risk of low engagement from stakeholders.

C.

Send documentation to the senior manager about the advantages of the new framework

D.

Escalate the senior manager's concern to the project sponsor and distribute the status to the team

Full Access
Question # 352

A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.

What should the project manager have done to prevent this conflict?

A.

Provided copies of the stakeholder engagement plan to all team members.

B.

Defined the roles and responsibilities of the team members.

C.

Updated the communications management plan.

D.

Established ground rules for the team

Full Access
Go to page: