Question # 393

A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water

What caused this situation to occur?

A.

The risk analysis was inadequate

B.

The project was completed behind schedule

C.

The requirements gathering was inadequate

D.

The project was delivered above budget

Full Access
Question # 394

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

A.

Mark the product backlog completion status and update the communications management plan.

B.

Ensure that knowledge transfer activities are executed as planned

C.

Release the resources and plan for a project completion celebration.

D.

Hold a steering committee meeting to inform them of the project completion

Full Access
Question # 395

A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard What should the project manager do?

A.

Review the project management plan

B.

Update the stakeholder engagement plan.

C.

Update the communications management plan

D.

Review the configuration management plan.

Full Access
Question # 396

A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget

What should the project manager do?

A.

Request to use the management reserve to keep the schedule

B.

Mitigate risks associated with the workaround to avoid project delays

C.

Proceed with the approved risk response plan.

D.

Discuss the options with the client as part of the change control process

Full Access
Question # 397

During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client

Match the scenario on the left with the action on the right.

Full Access
Question # 398

A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.

What action should the project manager take to motivate the project team's performance?

A.

Award certificates of appreciation to encourage the team

B.

Inform the team about the delivery pressure from the project sponsor

C.

Send a formal notice to team members instructing them to maintain performance

D.

Hire a few temporary team members to help with the additional work.

Full Access
Question # 399

A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped

What should the project manager do?

A.

Analyze both projects to determine the most effective use of common resources

B.

Use resource optimization to justify requesting more resources for the critical project

C.

Provide schedule optimization training to the project teams to improve their skills.

D.

Apply fast-tracking techniques to compress the schedule of the critical project

Full Access
Question # 400

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

A.

Increased bum rate

B.

Increased cost

C.

Increased technical debt

D.

Decreased efficiency

Full Access