Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 401

Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

A.

Ask for advice on how to be a better mentor to these team members.

B.

Set up a team building event to bring synergy back to the project team.

C.

Adjust the project manager's management style to better fit senior team members.

D.

Meet daily with each senior team member to monitor project status

Full Access
Question # 402

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?

A.

Schedule a meeting with all stakeholders to extend the project deadline

B.

Replace the vendor with a new vendor who can offer the component on time

C.

Add an item to the next status review to make stakeholders aware of the vendor issue.

D.

Review and update the issue log and determine if any alternative components can be offered

Full Access
Question # 403

The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?

A.

Review the project goal diagram with the team.

B.

Perform a stakeholder evaluation

C.

Confirm which templates the team should be using

D.

Review the risk management plan

Full Access
Question # 404

According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right

Full Access
Question # 405

A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter

What should the project manager do?

A.

Modify the baseline of the project for minor impact changes to the project scope

B.

Use a focus group and brainstorming sessions to gather more details about the project scope

C.

Register the changes in the configuration management plan and send it to the change control board (CCB).

D.

Explain to the sponsor that these requests could endanger the schedule and cost of the project

Full Access
Question # 406

A project manager at a company is considering a high-performing junior member of the organization to be the new project manager for a current project. What should the project manager do to prepare for a recommendation to senior management?

A.

Compile key highlights featuring the team member from the meeting minutes.

B.

Ask the team member to write a short biography listing their qualifications

C.

Gather project artifacts that demonstrate the team member's high performance

D.

Calculate the health of the projects on which the team member has worked

Full Access
Question # 407

A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?

A.

Persuade this stakeholder using emotional intelligence skills to obtain acceptance.

B.

Obtain final acceptance from another stakeholder who is also familiar with the project

C.

Escalate this issue to the project sponsor and ask for support in obtaining final stakeholder acceptance.

D.

Create a project acceptance waiver noting the stakeholder’s concerns so they can be addressed later

Full Access
Question # 408

During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path

What should the project manager do to avoid future delays?

A.

Submit a change request.

B.

Add additional resources to the project

C.

Update the scope of work.

D.

Review the risk management plan

Full Access
Go to page: