Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 409

A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease. What should the project manager do to address this issue?

A.

Force the team members to work from one location.

B.

Develop protocols for resolving conflicts between team members

C.

Obtain special expertise to advise the team members

D.

Set up face-to-face meetings with project team members

Full Access
Question # 410

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

A.

Recruit the best resources within the organization to be part of the virtual team

B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.

Identify the types and quantities of resources required for each work package or activity

D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.

Verify if team members are on more than one team and cannot devote enough time to this team

Full Access
Question # 411

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?

A.

The project is an information technology project and has minimal impact to the organization

B.

The project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).

C.

The project scope is well defined and the requirements are prioritized

D.

The project team has a colocated space and is capable of working together

Full Access
Question # 412

During daily calls team members share task progress One team member does not usually communicate many details and has critical tasks to be completed All team members are located in different countries and critical work is about to start Which two options will help the project manager in this situation? (Choose two)

A.

Encourage all team members to use a virtual workspace

B.

Ask the team to send emails with detailed task progress

C.

Talk to the team member about their engagement and take appropriate action.

D.

Reassign the work to a resource who participates in the daily calls

E.

Report the team member’s poor performance to the functional manager

Full Access
Question # 413

The project manager just started leading a project team from which the previous project manager resigned After a quick evaluation of the project it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule

What should the project manager do?

A.

Conduct a meeting with the project team to discuss and address the sources of disagreement

B.

Inform the stakeholders that the project will be delayed due to previous team management

C.

Crash the project timeline to ensure the project is back on schedule

D.

Issue a change request to extend the project schedule based on identified delays

Full Access
Question # 414

The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project

What should the project manager do to reduce negative impacts to the project?

A.

Modify the communications management plan to account for regional differences

B.

Conduct cultural awareness seminars

C.

Hold a virtual meeting to discuss the political environment.

D.

Conduct a multigenerational management training session

Full Access
Question # 415

In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.

What should the project manager do next1?

A.

Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder

B.

Inform the project sponsor that there are stakeholders who are not included in the communications management plan

C.

Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan

D.

Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.

Full Access
Question # 416

A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager’s project

Which two actions can the project manager take to bring the team back on track? (Choose two)

A.

Establish daily standups to review project progress and track the completion of deliverables

B.

Allow the team members to catch up at their own pace

C.

Alert the business stakeholders immediately of the schedule delay.

D.

Discuss the risk of project delay and work priorities with the respective functional managers

E.

Work with the team to identify options to accelerate project delivery.

Full Access
Go to page: