Halloween Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 337

During a sprint planning, the development lead highlights the importance of working on technical debt tasks that are critical for the product performance. However, the tasks will consume most of the team's capacity and they will not be able to work on product feature development.

What should the project manager do?

A.

Invite technical stakeholders for backlog prioritization.

B.

Work on the features already prioritized by the product owner.

C.

Ask the sponsor for more resources to continue at the same pace.

D.

Add the technical debt tasks to the sprint backlog.

Full Access
Question # 338

While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.

What should the scrum master do?

A.

Determine the average of the two estimates and assign that amount.

B.

Ask the product owner to rewrite the story so the final estimate can be agreed upon.

C.

Consult the lessons learned for insight into the correct estimate.

D.

Select the junior member's estimate since they will most likely be doing the work.

Full Access
Question # 339

A project manager is developing the project schedule with the project team. The team members estimate that an optimistic duration is 5 days, the pessimistic duration is 20 days, and the most likely duration is 11 days.

What duration should the project manager use?

A.

11 days

B.

12.5 days

C.

12 days

D.

11.5 days

Full Access
Question # 340

Due to their different ideas regarding the execution of a project, a conflict has occurred between two stakeholders.

What should the project manager do to resolve the conflict?

A.

Arrange a group meeting with the stakeholders to generate creative alternatives.

B.

Address the conflict in a planned meeting with all stakeholders and project team members.

C.

Assess the conflict based upon the stakeholders' past disagreements.

D.

Focus on the personal issues between the stakeholders.

Full Access
Question # 341

A project lead is managing an agile project. The project activities, which have been placed in a backlog, still need to be refined and prioritized.

What should the project lead use for backlog refinement considering the sprints are 2 weeks long?

A.

Sixty minutes every sprint going through stories with higher story points.

B.

Ninety minutes every three sprints going through stories that are higher priority.

C.

Sixty minutes every sprint going through stories that are higher priority.

D.

Ninety minutes every three sprints going through stories with higher story points.

Full Access
Question # 342

Generative artificial intelligence (AI) now helps produce documents on most projects across an organization and is yielding great benefits. Despite this change, a project manager notices that very few members of their current team know the AI tools available within the company. Consequently, they do not know how to use them effectively.

What should the project manager do?

A.

Identify more user-friendly generative AI applications in the industry and share with the team.

B.

Engage with some experienced personnel in the company and request they mentor the rest of the team.

C.

Document this issue as a lesson learned and hold a briefing at the end of the project.

D.

Invite the project sponsor to brief the team on the importance of generative AI and how to optimize the available applications.

Full Access
Question # 343

A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.

What should the project manager do to address the issue?

A.

Share a work performance report with the team member's supervisor.

B.

Assign a mentor to work with the senior team member.

C.

Speak with the senior team member to identify the difficulties.

D.

Collect feedback from all team members about team performance.

Full Access
Question # 344

A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.

What type of contract and project approach should the project manager consider?

A.

Time and materials (T&M) with an agile approach

B.

Cost reimbursable contract with a predictive approach

C.

Fixed-price contract with a predictive approach

D.

Memorandum of understanding (MOU) with an agile approach

Full Access
Go to page: