Question # 329

A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.

The project team will be virtual and will include members from different countries around the world.

What should the project manager do to ensure effective team building occurs?

A.

Coordinate with team members to define and communicate ways of working, roles and responsibilities, scheduling, time zone, and cultural

observance information.

B.

Explain to the team that since they are all SMEs and know one another, they are expected to immediately collaborate and deliver effectively.

C.

Update the communications management plan and determine an issue resolution process for when furture conflicts arise.

D.

Colocate the team members at the beginning of the project to explain the expectations for team interaction, meeting schedules, and overall

project governance.

Full Access
Question # 330

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Full Access
Question # 331

A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.

Knowing that there are no additional funds available, how should the project manager proceed?

A.

Allocate the budget to the phases of the project and meet with upper management to consolidate the final funds.

B.

Ensure that the budget is enough to cover the internal resources, since external supplies can be covered by procurement.

C.

Allocate the budget to the deliveries that have higher business value for the organization than those with lower business value.

D.

Decide to work on the small deliveries, leaving the big deliveries until the end of the project, and track critical expenses.

Full Access
Question # 332

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

A.

Use compression techniques to break down the scope and assign the scope pieces to

different vendors with a fixed-price contract.

B.

Use the contingency budget for hiring additional vendor resources to mitigate any project

risk.

C.

Engage in a time and materials (T&M) contract and hire a local vendor to support

development.

D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Full Access
Question # 333

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

A.

Discuss the vacation plan and include scheduling changes in the change log database.

B.

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.

C.

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.

D.

Push out the project timeline according to the vacation plan in place based on the recent company policy.

Full Access
Question # 334

A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline

What should the project manager do next?

A.

Select resources who are more experienced with the new technology

B.

Perform a root-cause analysis to measure how the new training will address the issue

C.

Include in the risk register a risk of unskilled resources for the new technology

D.

Elaborate and socialize the team charter as per the resource management plan

Full Access
Question # 335

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?

A.

Schedule a training course for the new team member to fill in their gaps in experience.

B.

Log this as an issue in the project issue log and speak with the resource manager.

C.

Provide weekly feedback to all project team members, including the new member.

D.

Ensure that coaching meetings are in place for this team member within the project timeline.

Full Access
Question # 336

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

A.

Review the project scope to align the project teams

B.

Review the resource management plan to align the project teams

C.

Review the project integration plan to align the project teams

D.

Review the work breakdown structure (WBS) to align the project teams

Full Access