Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 305

A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload

What should the project manager do to optimize the time of the resource who produces the progress reports?

A.

Work more closely with the agile team to eliminate the need for progress reports

B.

Record this in the issue log and find a resource to produce the reports

C.

Produce the progress reports on their own

D.

Engage a new resource to produce the progress reports

Full Access
Question # 306

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Full Access
Question # 307

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

A.

Work with the product owner to evaluate and prioritize the requirements

B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.

Determine the expected benefits of each requirement to maximize the overall business value

D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

Full Access
Question # 308

A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.

What should the project manager do next?

A.

Review the stakeholder engagement plan and communicate which technology is available to develop, transmit, and store project artifacts.

B.

Engage the software developer, let them work with this project management software, and then conduct a train-the-trainer activity to ensure everyone can use it.

C.

Research the project management software to understand how it works, and establish it as the acceptable software to hold the project artifacts.

D.

Review the communications management plan and communicate which technology is to be used to develop, transmit, and store project artifacts,

Full Access
Question # 309

A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.

What should the project manager do?

A.

Create an opportunity (or the project team to recognize this developer

B.

Send a recognition email to the team and copy management

C.

Reward the developer according to their motivations and interests

D.

Print a recognition certificate and present it to the developer during a meeting

Full Access
Question # 310

In the middle of an iteration, the product owner tells the agile team that the

government has updated legal requirements. This will result in some changes in the product

definition.

How should the project manager handle this situation?

A.

Review the iteration backlog because the product definition has changed and needs to

be reassessed before continuing the project.

B.

Continue work and ask the product owner to assess the changes and add/remove the

stories as needed in the backlog.

C.

Ask a business analyst to assess the changes and then add/remove the stories in the

backlog and prioritize them by business value.

D.

Ask the product owner to add new changes to the bottom of the backlog in order to

handle the modifications as a change request.

Full Access
Question # 311

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate

Full Access
Question # 312

A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO). The project manager

believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the

technology.

What should the project manager do?

A.

Engage stakeholders to modify policies outlined by the PMO.

B.

Move forward with the project governance and inform the PMO.

C.

Discuss the proposed changes with the PMO.

D.

Disregard the initial procedures and follow the policies outlined by the PMO,

Full Access
Go to page: