Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps
The key stakeholder of an agile project has low visibility of the project's progress. The stakeholder expresses a concern to the project manager about whether or not the scope is moving in the right direction.
What should the project manager do?
During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.
What should the project manager do next?
A project team is currently dispersed across multiple countries and time zones. Recent team feedback shows engagement levels are sub-optimal, and information flows are irregular and one-sided. There are also company travel restrictions in place, preventing physical colocation.
What improvements should the project manager implement to improve engagement?
A virtual product development team is working well together and is on schedule. One team member wants to take 1 week off to attend a training.
What should the project manager do?
A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.
What should the project manager do?
The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.
What should the project manager do first in this situation?
For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product
After collecting the new requirements, what should the project manager do?
Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)