Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 297

A customer calls the project manager to express concern about a project team

member who has been making changes within the live environment without approval. The

team member mentioned that the customer called and asked them to make the changes.

What should the project manager do next?

A.

Reinforce the value of documenting and approving all change requests and ask thecustomer to issue these through the agreed channels.

B.

Organize a meeting to mediate the relationship between the customer and the teammember to ensure no feelings are hurt.

C.

Ask the customer to email all requests directly to you and you will ensure they areactioned by the correct team member.

D.

Explain to the customer that the team member was just trying to help and the changescan be reverted if necessary.

Full Access
Question # 298

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

A.

Perform stakeholder engagement with the virtual team

B.

Add status reports to the communications management plan

C.

Convene an on-site meeting for both of the teams

D.

Add status report creation as a product backlog item

Full Access
Question # 299

A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.

What should the project manager do?

A.

Allow collaboration to smooth out communication between team members.

B.

Add collaboration tools to the communications management plan.

C.

Escalate these communication challenges to the project sponsor.

D.

Organize a team meeting to resolve the communication challenges.

Full Access
Question # 300

A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.

What should the project manager do?

A.

Investigate alternatives for team member needs.

B.

Evaluate the engagement needs for stakeholders.

C.

Identify the root cause of the team member's misunderstanding.

D.

Build trust and influence stakeholders.

Full Access
Question # 301

A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements.

The former project manager gave the new project manager a complete list of people to communicate with, and this client team member is not on it.

What should the project manager do?

A.

Update the communications matrix to ensure that client team member is included.

B.

Submit a change request to cover extra hours associated with project meetings.

C.

Increase the project meeting frequency and duration to allow for the extra work required.

D.

Speak with the client team member about the continuous delays during project meetings.

Full Access
Question # 302

An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.

What should the servant leader do?

A.

Escalate this to the project director for a resolution.

B.

Escalate this to the agile lead of the second team.

C.

Review the process and remove the impediment.

D.

Remove the certification need from the project scope.

Full Access
Question # 303

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

A.

Ask the team member to enter this potential schedule delay in the risk register.

B.

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges

C.

Actively listen to the team member and identify ways to support their needs in completing the tasks.

D.

Set up team-building activities with the project team members to reduce tension

Full Access
Question # 304

A project manager is managing a project in a fast-paced environment. The project manager needs to empower the team to collaborate toward an expected outcome and enable high-team performance. The CEO has suggested that the project manager apply a servant leadership style.

What should the project manager do to demonstrate the capabilities of a servant leader?

A.

Encourage all team members to develop the perfect plan to achieve the desired results.

B.

Create an environment where all team members compete to achieve the desired results.

C.

Assess the business case and define the project priorities to motivate all team members.

D.

Define the project's objectives and create an environment where all team members can succeed in achieving them.

Full Access
Go to page: