Halloween Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 273

A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as

a whole is low, especially in terms of group activities.

What should the project manager do?

A.

Negotiate for new team members.

B.

Review and update the communications management plan.

C.

Review and reassign team assignments.

D.

Facilitate communication and team building.

Full Access
Question # 274

A project manager who works for a company involved in several industries is asked

to lead a software development project for a government agency. The company attempted to

execute similar projects for other industries before but was unsuccessful.

What should the project manager do to ensure project success?

A.

Document this information in the risk management plan.

B.

Develop a contingency plan to prepare for possible risks.

C.

Continue executing the project using expert judgment.

D.

Review the lessons learned registers from the previous projects.

Full Access
Question # 275

A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?

A.

Mass communication

B.

Push communication

C.

Pull communication

D.

Interactive communication

Full Access
Question # 276

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

A.

Work with the team and others in the network to assess and prioritize the obstacles.

B.

Engage with the external stakeholders and the other division of the organization toresolve the issues.

C.

Escalate the obstacles to the project sponsor for assistance with resolution.

D.

Determine a change response to identify and resolve the obstacles to move the projectforward.

Full Access
Question # 277

A project manager is leading an electrical project that spans five towns. The project

manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.

What should the project manager do?

A.

Change the project scope and seek approval to exclude this town from the overallproject.

B.

Engage with the town's authorities to discuss the reason for the change in commitmentand agree on a solution.

C.

Instruct the team to move to the next town and continue the project to avoid further delays.

D.

Retrieve all minutes of stakeholder engagements and send to the town as a reminder of their commitment to the project.

Full Access
Question # 278

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

A.

Meet with the stakeholder to discuss the impact of the deliverable

B.

Consider the stakeholder as a risk and evaluate possible solutions with the project team

C.

Improve communication with the stakeholder to obtain their assistance in the future

D.

Escalate to the project sponsor due to the political nature of the issue

Full Access
Question # 279

A company has always acquired very specialized services from local companies for

its projects. During the planning stage for a regulatory project, the project manager is informed

that local vendors would not be able to operate due to an unexpected major event. There is an

option to hire the same services from companies in other countries.

What should the project manager do in this situation?

A.

Plan to execute the procurement tasks in a virtual environment.

B.

Review organizational process assets (OPAs) for similar projects.

C.

Create a change request to extend the duration of the project.

D.

Ask the project sponsor to put the project on hold.

Full Access
Question # 280

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

A.

Encourage and motivate the team with project incentives

B.

Subdivide the team to handle different aspects of the project

C.

Support the team to find and execute the minimum viable product (MVP)

D.

Organize project execution to satisfy the project sponsor s request

Full Access
Go to page: