Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 241

A key stakeholder of a project wants to include additional work before completion.

What should the project manager do?

A.

Request the additional work through governance.

B.

Meet with the stakeholder and explain that additional work cannot be added.

C.

Prioritize the additional work in the backlog.

D.

Collaborate immediately with the stakeholder to complete the additional work.

Full Access
Question # 242

A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty

What should the project manager have done to avoid this situation?

A.

Ensured the team charter was developed by the team members

B.

Ensured the team members are fully supportive of all decisions.

C.

Distributed the project charter to all team members.

D.

Used a charismatic leadership style

Full Access
Question # 243

A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.

What should the project manager do?

A.

Hold separate retrospective meetings for both the vendor team and the internal team.

B.

Schedule a preliminary meeting with the account manager from the vendor and the test manager.

C.

Establish a clear agenda for the meeting and remind the vendor and internal teams that the scope is to improve the process.

D.

Invite the procurement manager and a representative from the vendor to manage the current tense relationship.

Full Access
Question # 244

A project manager who has been working on an ongoing volatile project is retiring. A new project manager is collaborating with the retiring project manager to ensure a smooth transition.

What should the new project manager first discuss, review, and clarify during the transition meetings?

A.

Resource management plan

B.

Change management plan

C.

Lessons learned log

D.

Risk register

Full Access
Question # 245

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

A.

Execute the smaller estimated activities.

B.

Resize the story points.

C.

Negotiate the estimation so it gets smaller.

D.

Break down the larger activities into smaller ones.

Full Access
Question # 246

A project manager was appointed to lead an already approved project. While reviewing the benefits management plan, the project manager finds out that the information about the forecasted value of the project may not be accurate.

What should the project manager do?

A.

Meet with the project sponsor and key stakeholders to confirm that the information about the forecasted project value is accurate.

B.

Ask the organization to cancel the project because the project manager is unable to confirm that the project will deliver the forecasted value.

C.

Proceed with execution of the project whether the information about the forecasted value is right or not because the project is already approved.

D.

Develop scope alternatives to achieve the forecasted project value in the event that project benefits information is inaccurate.

Full Access
Question # 247

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items

What should the project manager do as a servant leader?

A.

Ask the sponsor to submit a change request to the change control board (CCB)

B.

Support the product owners decision to change the priority of the product backlog items

C.

Accept the request and include the product backlog items in the next sprint

D.

Review the impact of the change on the schedule management plan baseline

Full Access
Question # 248

During a project iteration, half of the project team was reallocated to a new project. How should the project lead handle the situation?

A.

Raise the risk of having the velocity impacted for the current iteration and discuss it with the product owner.

B.

Raise the issue with the product owner to bring additional resources to the project team.

C.

Raise the risk with the project stakeholders and wait until the velocity for the current iteration is calculated.

D.

Raise the issue with the project stakeholders to analyze the project impact and take the proper actions.