Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 257

A project team is defining the ground rules during their first meeting as a team. During this session, only a few of the team members suggested and approved the ground rules while most remained silent. As a result, the team's ground rules favor those few team members.

What should the project manager do?

A.

Conduct a round table and ask the team to share their opinions one by one.

B.

Propose new team ground rules and communicate them to all.

C.

Ask the silent team members to share their opinions via email.

D.

Perform focus group interviews based on the new team ground rules.

Full Access
Question # 258

A project manager is establishing a project management office (PMO) for a

company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.

Which activity should the project manager use to help train the stakeholders?

A.

Contract negotiation

B.

Team assessment

C.

Mentoring and coaching

D.

On-the-job training

Full Access
Question # 259

A protect manager is struggling to obtain participation from key stakeholders who do not usually attend project meetings What should the project manager do1?

A.

Distribute the communications management plan

B.

Reschedule meetings lo align with the stakeholders' availability

C.

Escalate the issue to senior management

D.

Set clear meeting expectations by sharing agendas in advance

Full Access
Question # 260

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Full Access
Question # 261

A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?

A.

An agreed-upon work method and tools that should fit the business need and project constraints

B.

A detailed mitigation plan on the risks for each work method and the tools used

C.

A consensus that everything will run as anticipated once the tools and work methods are identified

D.

A technology roadmap for creating similar deliverables in the future with the same tools

Full Access
Question # 262

An agile project is completing its second sprint and products are being finished. However, two groups with different levels of expertise disagree on the backlog priority.

What should the project manager do first to resolve this dispute?

A.

Escalate to the project sponsor to provide a solution to the conflict.

B.

Interpret the source and stage of the conflict and select a resolution approach.

C.

Apply a compromising resolution approach, involving both groups.

D.

Ask the functional managers of both groups to help find a workable solution.

Full Access
Question # 263

A transformation project that is composed of agile streams has come to an end.

How should the project manager collect the experience gained during this project?

A.

Organize a lessons learned session with the team.

B.

Create a document with the information from the last sprint retrospective.

C.

Ask for feedback during the next standup meeting.

D.

Conduct a session with the members of the project steering committee.

Full Access
Question # 264

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

A.

Provide mentoring for the key team members on agile practices and support the teamwith training and encouragement.

B.

Create an agile conduct guideline and ensure that all team members follow the rulesstated in the document.

C.

Replace the key team members with new resources who are already aware of the agilemindset.

D.

Provide directions to the team members on how to accelerate the company'stransformation, bringing the project back on track.

Full Access
Go to page: