Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 249

A Scrum team has information radiators but must also keep stakeholders aware of their progress. In addition, the project management office (PMO) has specific templates for status reporting to management. The project lead realizes that a variety of reporting will be needed to satisfy enterprise and stakeholder needs.

What should the project lead do?

A.

Determine the minimum communications needed for the project, and adapt the communication plans as needed.

B.

Document only the plan for written communications, and send meeting invites for verbal communication sessions.

C.

Follow the project management office (PMO) guidelines for communications instead of generating a project communications management plan.

D.

Create a communications management plan informing all project team members and stakeholders who will receive what type of communication.

Full Access
Question # 250

A team is performing above expectations, and the sponsor wants to expand the project scope to benefit the organization. However, there are only a few team members with the needed leadership experience.

What should the project manager do?

A.

Communicate the risks and propose hiring members with leadership experience before continuing with the request.

B.

Decline the scope expansion until the team members get appropriate leadership opportunities within the project.

C.

Implement the scope expansion and suggest the team members get a mentor due to their lack of leadership experience.

D.

Recognize each team member for their contributions and recommend them to the leadership development program.

Full Access
Question # 251

A project is in the execution phase and there are disagreements between two key stakeholders about the project's scope. One stakeholder is adamant about expanding the scope and the other stakeholder is content with the current arrangement.

What should the project manager do?

A.

Escalate the stakeholder's conflict to senior management so they can resolve the issue.

B.

Schedule a one-on-one discussion with each stakeholder to understand their concerns.

C.

Schedule a meeting with both stakeholders to encourage dialogue and reach a decision.

D.

Suggest that the two stakeholders meet together to agree upon a project scope.

Full Access
Question # 252

A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?

A.

Replan the remaining iterations according to the new installation dates

B.

Update the product backlog m order to address the delays

C.

Review the procurement agreements to address the situation

D.

Find another vendor who can fulfill the delivery dates

Full Access
Question # 253

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.

What should the project manager do next?

A.

Escalate the obstacle to a servant leader for resolution.

B.

Make changes to reprioritize the backlog because of the obstacle.

C.

Reject the obstacle and present the partial solution to the customer.

D.

Focus on generating business value despite the obstacle.

Full Access
Question # 254

During the execution of a project, a project manager is informed that a team member is leaving the company. What should the project manager do next?

A.

Wait for the next project status meeting to evaluate the impact of one less resource.

B.

Ask the project sponsor to replace the resource immediately.

C.

Record the situation in the issue log immediately and evaluate the impact of losing the resource.

D.

Freeze the activities of the lost resource until they are replaced.

Full Access
Question # 255

A project manager is appointed to manage an infrastructure project that spans

across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

A.

Discuss the concerns with the project sponsor and modify the project charter to includemore budget for interactions.

B.

Plan a communication method and allow the project team members to virtually interact.

C.

Create a social media group platform for the team to create a supportive environment.

D.

Set the ground rules and identify a contingency plan in the risk register.

Full Access
Question # 256

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

A.

Instruct the team to work as planned and Ignore the stakeholder's requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

Full Access
Go to page: