Winter Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 161

A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?

A.

Meet with the project team to forecast the SPI trend to determine if there are funds available to pay the 30 team members.

B.

Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.

C.

Inform the project team that since the CPI is trending downward, there are funds available to expand the team.

D.

Engage with the human resources (HR) representative to begin selecting candidates for the 30 open positions.

Full Access
Question # 162

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

A.

Ask the project team to review and modify all of these reports.

B.

Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.

C.

Explain to the stakeholder that these are the approved templates for the reports.

D.

Ensure that the reports comply with the communications management plan.

Full Access
Question # 163

A project manager is leading a project with a team that is comprised of both experienced and inexperienced team members. What should the project manager do to ensure an effective project team?

A.

Ask the least experienced team members to work as assistants to the more experienced team members so they can gain some project experience.

B.

Ask the project sponsor to replace the least experienced team members with more experienced ones.

C.

Identify how the team members with no experience can contribute according to their capabilities and provide training if needed.

D.

Assign critical project tasks to the most experienced team members as they are the only ones with the knowledge.

Full Access
Question # 164

A project team Is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned.

What should the project manager do?

A.

Discuss with the team how the project objectives can be met.

B.

Request that the sponsor increase the bonus for high performers.

C.

Schedule a team-building activity to boost the team's morale.

D.

Organize a team meeting to remind the team of the ground rules.

Full Access
Question # 165

Customers are concerned about the quality of an interim software system for a project. The quality control team has approved the software, but the customers are complaining that some functions do not comply with the requirements.

What should the project manager do to prevent this from happening again?

A.

Review the risk impact of quality nonconformance.

B.

Review the communications management plan.

C.

Revise the quality management plan.

D.

Revise the product acceptance specifications.

Full Access
Question # 166

A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues.

What should the project manager do?

A.

Use the compliance issues to identify coaching and mentoring opportunities.

B.

Log the feedback from the compliance gaps in the lessons learned register.

C.

Review this with the project sponsor to avoid compliance gaps and issues.

D.

Discuss the suggestions with the staff responsible for the compliance issues.

Full Access
Question # 167

A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.

What should the project manager do next?

A.

Guide the team to determine alternatives.

B.

Move the dependent task to the next iteration.

C.

Escalate the issue to the company's IT manager.

D.

Escalate the issue to the project sponsor.

Full Access
Question # 168

A team member mentions to the scrum master that the user stories are too long. The team member believes this may be the cause of the team's inability to deliver value for stakeholders.

What should the scrum master do?

A.

Review the user stories with the team and ask the product owner to break them down into more manageable units.

B.

Review the user stories with the stakeholders and ask the product owner to break them down into more manageable units.

C.

Ask the team member to suggest using shorter user stories to the product owner so that the next sprint can move faster.

D.

Ask all the team members for their views about using shorter user stories so that value can be created for stakeholders.

Full Access
Go to page: