Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 129

During the early phases of a project, mitigation actions were not executed in a

timely manner; therefore, the project schedule was impacted. Several project stakeholders are

now frustrated with the delays.

What should the project manager have done to manage the issue?

A.

Identified and reported the issue

B.

Monitored and controlled the issue

C.

Identified the appropriate response and had it implemented

D.

Communicated any identified action to impacted stakeholders

Full Access
Question # 130

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?

A.

Functional managers, team members, and external consultants with experience in the field

B.

Team members, engineers, and weather experts

C.

Team members, consultants from outside the project with experience in the field, and the customer

D.

Weather experts, functional managers, and team members

Full Access
Question # 131

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

A.

Include additional mitigation actions against feature defects and update the risk management plan.

B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Full Access
Question # 132

During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected What should the project manager have the project team do first to address the issue?

A.

Update the issue log and document the change

B.

Review the product specification requirements.

C.

Perform a root cause analysis

D.

Submit a change request for corrective action.

Full Access
Question # 133

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?

A.

Become a servant leader by supporting team collaboration and removing impediments

B.

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration

C.

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination

D.

introduce new communication tools to the project team members

Full Access
Question # 134

In an agile team, some of the team members are coming forward to ask for more

autonomy on the project. What should the project manager do in this situation?

A.

Encourage the team members to make decisions.

B.

Discourage them as conflicts may be created.

C.

Encourage the team lead to make decisions.

D.

Discourage this request, as it is for the management team.

Full Access
Question # 135

A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.

What should the project manager do?

A.

Provide a software for instant messaging.

B.

Document all information on the team wiki.

C.

Promote the use of remote site syndication.

D.

Facilitate regular conference calls.

Full Access
Question # 136

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

A.

Seek the sponsor's approval to extend the project schedule.

B.

Set up a meeting to perform a root cause analysis.

C.

Update the issue log and communicate it to the team.

D.

Permanently colocate the team for better performance.

Full Access
Go to page: