Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 169

In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.

What should the project manager do first?

A.

Escalate the issue to the change control board (CCB).

B.

Ask the project team to analyze the impact.

C.

Register the risk and document the contingency plan.

D.

Have the project team brainstorm alternatives.

Full Access
Question # 170

When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined. What should the project manager do?

A.

Work with the business analysts to track and collect the missing data and build the KPIs.

B.

Coordinate with the benefit owner to track and collect the missing data and build the KPIs.

C.

Forward the issue to the benefit owner and ask them to collect the missing data and build the KPIs.

D.

Ask the program manager to track and collect the missing data and work to build the KPIs.

Full Access
Question # 171

An organization's human resources (HR) department wants to create a high-performing team and implement a project that includes job grading, organizational restructuring, and soft skills training.

To ensure the quality of the project deliverable, which three actions should the project manager take? (Choose 3)

A.

Collect feedback and conduct surveys and questionnaires.

B.

Hire a certified expert to lead the project quality process.

C.

Document quality gaps and analyze them for continuous improvement.

D.

Develop a proper quality management plan with measurable metrics.

E.

Apply an existing external framework for performance improvement.

Full Access
Question # 172

A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?

A.

Review the cost and schedule baselines for execution.

B.

Define change management for the new technology.

C.

Analyze the cost and identify the project benefits.

D.

Identify the risks in implementing the new technology.

Full Access
Question # 173

A project team is concluding the final sprint to deliver two work packages. However, the scrum master has not scheduled sprints for three packages on the critical path, which is going to cause the schedule performance index (SPI) to trend toward 0.90 the following month.

What should the project manager do first?

A.

Evaluate the schedule performance index (SPI) trend for slack to enable all five sprints while maintaining the cost performance index (CPI).

B.

Instruct the scrum master to suspend the current sprints and initiate the critical sprints immediately.

C.

Ask the scrum master to identify why sprints are in process for work that is not on the critical path.

D.

Contact the project sponsor to request adjustment to the completion date and to enable the current workflow.

Full Access
Question # 174

A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.

Which three actions should the project manager take? (Choose 3)

A.

Develop the project management plan based on the requirements requested by the customer.

B.

Develop the application as requested by the customer, based on the approved project requirements.

C.

Plan a minimum viable product (MVP) to get early feedback from the customer.

D.

Facilitate a focus group to assess the functionality before development.

E.

Use an agile approach to deliver the product based on sprints.

Full Access
Question # 175

A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

A.

Ask the sponsor to increase the budget and schedule of the project to accommodate the additional scope.

B.

Encourage the sponsor to start another project for the additional location so that the current project is not impacted.

C.

Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project.

D.

Discuss with the sponsor that the project scope is approved and it is not possible to include two locations as it will affect the budget.

Full Access
Question # 176

A project manager has just been assigned a major, ongoing project. The project team is not working in harmony and their performance is decreasing. Some team members are autocratic in their approach whereas others are in avoidance mode.

How should the project manager proceed?

A.

Emphasize their autonomy as project manager, implying that they will not allow team disunity.

B.

Appeal for cooperation from all of the team members, emphasizing the benefit of the project outcome to the company.

C.

Assess the various team behaviors through the use of personality indicators to appropriately deal with each personality type.

D.

Request for removal of the autocratic members who obviously are not interested in the project.