Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 185

A project to develop an enterprise resource system for a university is in the planning phase. The project has internal stakeholders such as operational departments, students, and academic staff, as well as global stakeholders who receive the information from the university on a regular basis. All the stakeholders have very different expectations and needs from the system.

What should the project manager do to ensure effective communication?

A.

Plan to implement a united communication platform, where all information about the project will be shared and updated regularly.

B.

Ensure all the information about the project implementation is provided to all of the different stakeholders in a unified communication format.

C.

Define communication target groups and provide information, messages, channels, and the frequency of communication for each group.

D.

Arrange an information session for all of the stakeholders about the plans for handling their various communication needs.

Full Access
Question # 186

A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office's (PMO's) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO's status reports have sufficient enough information

How should the new project manager proceed*?

A.

Continue using the outgoing project manager's status reports as well as their approach for schedule reporting

B.

Explain to the PMO that the hybrid project team needs to keep an agile approach for reporting and will not be complying with the organizational standard

C.

Change the status reports according to the template supplied by the PMO and proceed with scheduled reporting

D.

Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

Full Access
Question # 187

A project manager is overseeing a 10-mile piping installation project that was supposed to spend US$15,000 per mile of piping installation and should complete the project exactly 20 weeks from its start. The project manager just found out that only 80% of the work has been completed.

What is the budget at completion (BAC)?

A.

US$100,000

B.

US$150,000

C.

US$300,000

D.

US$250,000

Full Access
Question # 188

A project manager is in the middle of executing the construction of a high-rise plaza when the government regulatory agency announces an increase in the price of fuel. The project still has seven months left on the schedule.

What should the project manager do first?

A.

Meet with the vendors to evaluate the impact on the budget.

B.

Implement crashing to mitigate the impact on the budget.

C.

Review the organizational process assets (OPAs) as a reference.

D.

Request the release of management reserve for the project.

Full Access
Question # 189

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

A.

Add more items to the sprint backlog that will add value.

B.

Complete the sprint and seek a waiver from the regulator.

C.

Complete the sprint, but do not release the deliverable.

D.

Perform a sprint risk assessment and analyze challenges.

Full Access
Question # 190

In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market

while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.

What should the project manager do to avoid a reoccurrence of this scenario?

A.

Ensure the content of the project report is clearly understood and request any necessary feedback.

B.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.

C.

Send a detailed report to each steering committee member ahead of the meeting.

D.

Ensure that all product features are completed as per the communicated specifications before releasing to market.

Full Access
Question # 191

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?

A.

Add a fixed number of change requests allowed by the client on the project baseline.

B.

Request sponsor approval for all change requests to reduce the number of changes.

C.

Initiate the number of iterations to reduce the number of change requests.

D.

Reduce the number of approvers required to implement a change request.

Full Access
Question # 192

There is a problem with a project because some features are not in compliance with

regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?

A.

Review the stakeholder engagement assessment matrix to determine next steps.

B.

Set up some time with the stakeholders to explain the importance of compliance.

C.

Meet with the sponsor to discuss how to handle the stakeholders' differing opinions.

D.

Send out documentation to align stakeholder expectations and project objectives.