Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 121

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Full Access
Question # 122

A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

A.

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Full Access
Question # 123

A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget

What should the project manager update first?

A.

Issue log

B.

Lessons learned register

C.

Stakeholder engagement plan

D.

Risk register

Full Access
Question # 124

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

A.

Update the stakeholder register.

B.

Refer to the resource management plan.

C.

Consult the project sponsor.

D.

Modify the statement of work (SOV).

Full Access
Question # 125

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

A.

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution

B.

Call a team meeting to discuss team members' strengths and weaknesses

C.

Establish rules and regulations for team members with consequences if the goals are not reached

D.

Establish team behavior and develop an understating of how to work together

Full Access
Question # 126

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?

A.

Avoid the conflict as the customer feels comfortable with using processes from

company A.

B.

Review the historical information and make the decision based on the return on

investment (ROI).

C.

Ask the team to use company B's processes since they are more familiar with these

processes.

D.

Work with the team to analyze which processes are suitable to use and define them in

the ground rules.

Full Access
Question # 127

A project sponsor asks the project manager to explore a hybrid approach for a new

project. The product manager for this project has already prepared a detailed specification for the product.

What should the project manager do to proceed with the project management plan?

A.

Ask the team to assess whether the product specification can be expressed in user

stories to enable a Scrum or Kanban approach.

B.

Explore with the product manager to determine if there are viable opportunities to

deliver value incrementally and increase business value.

C.

Recommend to the project sponsor that a predictive approach is appropriate for the

project due to the stable product requirements.

D.

Ask the product manager whether they are prepared to act as product owner for the

project in order to participate in iterative planning and reviews.

Full Access
Question # 128

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

A.

Replace the team member immediately to maintain a good relationship with the

functional manager.

B.

Discuss the issue with the functional manager to understand the reason for the

complaint.

C.

Support the team member and provide documentation to the functional manager

proving their performance.

D.

Protect the team member and ask the project sponsor to minimize any external

interruptions.

Full Access
Go to page: