Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 177

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?

A.

Develop new procedures that are easy for the team to follow.

B.

Escalate the issue to the CEO and the board members.

C.

Instruct the team that the procedures should always be followed.

D.

Initiate a review of the procedures with the CTO and the team.

Full Access
Question # 178

A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.

What should the project manager do to ensure the velocity is under control?

A.

Ask the product owner to look at a minimum of four to eight iterations and replan the velocity for the next iteration based on the team's current performance.

B.

Ask the scrum master to plug gaps in the team's performance by adding a team member to compensate for the velocity decrease.

C.

Request that the team improve their cycle time to compensate for the velocity decrease.

D.

Request the team to improve the lead time, cycle time, and response time individually and track closure.

Full Access
Question # 179

An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.

Which ceremony should be used in developing this register?

A.

Sprint plans

B.

Retrospective results

C.

Sprint report

D.

Project status report

Full Access
Question # 180

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

A.

Accept risks as they decrease over a period of time.

B.

Create a risk value profile to track the relative importance of risks.

C.

Log and track risks separately as only business value is important.

D.

Assess risks together with business value during prioritization.

Full Access
Question # 181

A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?

A.

Request the team member to move to another team.

B.

Delegate other team members to complete this team member's tasks.

C.

Mentor the team member and provide the necessary training.

D.

Include this team member in an improvement program through a human resources request.

Full Access
Question # 182

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

Full Access
Question # 183

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

A.

Accommodate the change request to serve the client's needs

B.

Consult with team members and allow them to make a decision

C.

Convince the client not to make changes to the project

D.

Make transactional decisions focusing on the project goals

Full Access
Question # 184

A project sponsor has requested a trend analysis of all risks that the project has

monitored over the past 12 months. What should the agile project manager do?

A.

Share the annual report with the sponsor.

B.

Organize a stakeholder meeting to brainstorm on general project risks.

C.

Extract this from the project risk register tracking tool and issues log.

D.

Refer the sponsor to the contract document.

Full Access
Go to page: