A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.
What immediate action should the project manager take to improve the situation?
In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.
What should the project manager do?
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?
A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.
What should the project manager do?
A new project manager has been assigned to an environmental project. After
reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.
Why is this situation problematic?
At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?
An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work
What should the project manager do?
A project manager is in the process of creating a strengths-based team and is
organizing a series of workshops to identify and document the strengths of each project team
member. During this session, there are multiple team members who are not actively
participating. These meetings are becoming futile due to a lack of participation.
What should the project manager do?