New Year Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 457

A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time

What kind of conflict resolution did the project manager apply in this situation?

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Collaborate/problem solve

D.

Force/direct

Full Access
Question # 458

A project manager finds out that the required project status reports have not been

filled out by most team members. These status reports are urgently needed to compile a

comprehensive status report for the project sponsor.

What should the project manager do to address this situation?

A.

Reprimand the team members who did not fill out the status reports.

B.

Justify the team members' behavior to the project sponsor.

C.

Quickly put together a report that will satisfy the project sponsor.

D.

Discuss the issue with the team members at fault.

Full Access
Question # 459

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?

A.

Analyze the problem with both teams to figure out If pan of the work must be redone.

B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.

C.

Demand that the business team stop wasting time and define final requirements for the product.

D.

Tell the business team and Scrum team to continue following the initial plan.

Full Access
Question # 460

During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements

Which technique should the project manager use to resolve this issue?

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Force/direct

D.

Collaborate/problem solve

Full Access
Question # 461

During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?

A.

Add the stakeholder details into the periodic reports and update the project management plan

B.

Invite the stakeholder to all future project review meetings and update the project management plan

C.

Update the project management plan with the new information and inform all of the relevant stakeholders

D.

Meet with the stakeholder to better understand their expectations and update the stakeholder engagement plan

Full Access
Question # 462

A team is given an agile project to build a conceptual product for a new customer.

While planning, the project manager is trying to determine the best way to show value to the

customer, as the technical requirements are not very detailed.

What should the project manager do to help the client understand the value delivered during

project execution?

A.

Include a planned value (PV) calculation in the sprint report for each build cycle.

B.

Conduct a customer demonstration at the end of each build cycle.

C.

Provide the customer with the refined specification during each build cycle.

D.

Show the customer a sprint burndown chart for each build cycle.

Full Access
Question # 463

During project execution, an important stakeholder threatens to withdraw support

for the project, citing a lack of transparency and accountability in the way the project is being

executed. What should the project manager do to handle this situation?

A.

Approach the stakeholder to address the concerns.

B.

Consult the risk management plan.

C.

Escalate the issue to the project management office (PMO).

D.

Refer the stakeholder to the project sponsor.

Full Access
Question # 464

An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work

What should the project manager do?

A.

Escalate the situation to the engineer's manager

B.

Request external training for the engineer

C.

Request external training for the engineer and designer

D.

Allow the engineer and designer to cross-train with each other

Full Access
Go to page: