Month End Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Go to page:
Question # 489

A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email

What should the project manager do?

A.

Contact the sponsor to request direction regarding the communication tool to be used by the project team

B.

Update the communications management plan based on the product owner’s

preferences and distribute to the team

C.

Suggest to the team to start using the communication tool suggested by the product owner

D.

Request the product owner to use email because using another tool will increase the workload

Full Access
Question # 490

The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.

What does that project manager need to do to make the team work in a collaborative way?

A.

Request the project management office (PMO) for a team of mentors.

B.

Allocate time to mentor the team.

C.

Update the issue log.

D.

Identify any training gaps

Full Access
Question # 491

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

A.

Ask the stakeholders about the priority of this change

B.

Ask the product owner to review the product backlog

C.

Ask the team members to analyze the impact of this change

D.

Ask the sponsor to approve the change request

E.

Ask the team members to include the change in the next iteration

Full Access
Question # 492

The following table shows the business value created and the development effort required to implement various features in a product

Which feature should the team prioritize first? Enter the feature name in the box below

Full Access
Question # 493

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

A.

Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Full Access
Question # 494

A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources

and has appointed a project manager.

What should the project manager recommend that the CEO do first?

A.

Create a framework to justify project execution.

B.

Utilize an agile approach for all upcoming projects.

C.

Create a framework to support project success.

D.

Utilize a predictive approach for all upcoming projects.

Full Access
Question # 495

A company wants to show the commercial advantages of a product in a competitive market. They commissioned a project team to create a prototype. The team is building the prototype incrementally.

What should the project manager set as a priority?

A.

Implement the plan-do-check-action (PDCA) cycle.

B.

Deliver business value as soon as possible.

C.

Emphasize the use of Kanban methods.

D.

Ensure that the project sponsor knows the schedule.

Full Access
Question # 496

A team member increased the estimated completion time for their activities on the critical path. This action, however, has caused friction among the team members. The project manager reviewed the key performance indicators (KPIs) that show the issue.

What should the project manager do first?

A.

Conduct a root cause analysis (RCA) and plan the correct actions to ensure completion of the tasks on time.

B.

Allocate another resource to help the team member to complete the tasks and meet the estimated activity time.

C.

Train the team member in the methodology to get the sufficient knowledge to meet the estimated activity time.

D.

Apply crashing to the strategic tasks to recover any time that was lost to bring the project on track.

Full Access
Go to page: