Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 441

An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?

A.

Add the competitor's functionalities to the product backlog to improve the product

B.

Ask the sponsor to add more people to the team

C.

Help the team to find a new approach to launch the product as soon as possible

D.

Ask the team to increase the velocity to launch the product as soon as possible

Full Access
Question # 442

A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.

How can the project manager prevent this situation from happening in the future?

A.

Create a prioritized backlog and define iteration review sessions with stakeholders

B.

Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders

C.

Schedule a daily meeting to review team performance and impediments

D.

Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders

Full Access
Question # 443

A project manager is m the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence The project is ahead of schedule and running under budget

Which two actions should the project manager take initially to resolve this problem? (Choose two)

A.

Check the risk register for a prepared response to a resource being suddenly unavailable.

B.

Check if the team member's activities are sufficiently documented to facilitate handover

C.

Check the project's responsibility assignment matrix (RAM) to determine which activities will be affected

D.

Reassign responsibilities across the remaining members using the available float for training.

E.

Obtain the project sponsors support to replace the team member on leave

Full Access
Question # 444

A company has a lot of experience with predictive projects The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.

What should the project manager do?

A.

Prepare and submit a status report to the steering committee to update performance monitoring

B.

Determine the data to be monitored during the project as well as the expected performance and targets.

C.

Update the communications management plan to consider performance review meetings with the project stakeholders

D.

Conduct reviews with stakeholders to discuss the potential benefits the approach may have to the project

Full Access
Question # 445

for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.

What should the project manager do next?

A.

Accept the proposed replacement in order to keep procurement activities on track

B.

Insist on using the component per the project specifications and air freight the equipment to mitigate the delay

C.

Instruct the vendor to use the part that is compliant with the project specifications and update the schedule

D.

Consult with a subject matter expert (SME) to see if the proposed change isacceptable

Full Access
Question # 446

A project just kicked off and management’s expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?

A.

Increase the details of the work breakdown structure (WBS) to minimize errors and delays.

B.

Split the backlog into phases to ensure that the key features are delivered first

C.

Ask the sponsor to prioritize some functionalities of the product.

D.

Identify the minimum functionality required for the product

Full Access
Question # 447

During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client

Match the scenario on the left with the action on the right.

Full Access
Question # 448

A project manager at a company is considering a high-performing junior member of the organization to be the new project manager for a current project. What should the project manager do to prepare for a recommendation to senior management?

A.

Compile key highlights featuring the team member from the meeting minutes.

B.

Ask the team member to write a short biography listing their qualifications

C.

Gather project artifacts that demonstrate the team member's high performance

D.

Calculate the health of the projects on which the team member has worked