Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 481

A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager

What should the project manager do first in this situation'?

A.

Ask the functional manager why a decision was made without consulting them

B.

Use soft skills to influence the team member to slay until the project is completed

C.

Ask the functional manager for an immediate replacement for the team member.

D.

Review the risk management plan and mitigation plan to understand the impact of this issue

Full Access
Question # 482

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add it as an issue in the issue log

C.

Direct the sales team to speak with accounting to resolve the issue

D.

Escalate the issue to the functional manager

Full Access
Question # 483

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

A.

Maintain a central repository of artifacts with a version control system.

B.

Maintain separate document control via regions to avoid discrepancies.

C.

Develop a document management software for version control.

D.

Facilitate training on version control and project artifacts,

Full Access
Question # 484

During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?

A.

Document the issues and extend the project delivery timeline.

B.

Convene the steering committee and inform them of the impact to the project.

C.

Prioritize the user stories with issues and have the team resolve them

D.

Update the project management plan and risk management plan.

Full Access
Question # 485

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

A.

Create an issue log template that will be used to identify and track impediments.

B.

Create a contingency plan in case the project deviates from the initial plan.

C.

Create a schedule management plan to ensure the project meets the delivery date.

D.

Create an assumption log and map assumptions to impediments based on the impact tothe project value.

Full Access
Question # 486

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

A.

Support the team member by removing the blockers and impediments.

B.

Allocate the blockers and impediments to the product owner to resolve.

C.

Insist that the person who raised the blockers and impediments take ownership.

D.

Add any blockers or impediments to the risk register,

Full Access
Question # 487

A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.

What should the project manager do?

A.

Process a bank loan to pay the payroll of the third-party supplier.

B.

Reassign resources from other projects to pay the third-party supplier.

C.

Explain the third-party supplier situation to the client and request payment.

D.

Inform the client that the project must be delayed until payment is received.

Full Access
Question # 488

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?

A.

Planned all required training for the team during the onboarding process

B.

Identified all required skills after the kick-off of the project

C.

Identified all required skills during the planning of the project

D.

Asked the sponsor to identify all required skills during the planning of the project