Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 465

A project to develop an enterprise resource planning (ERP) system for a university is ongoing. The system should improve business processes through digitalization and elimination of human errors, and also provide end users with simplified and easily accessible services. What should the project manager do to ensure achievement of the intended business value?

A.

Evaluate each change request and review the business case each time

B.

Evaluate deliverables against the business case continuously

C.

Evaluate deliverables against the business case at the end of the life cycle

D.

Evaluate customer feedback and review the business case each time

Full Access
Question # 466

A project manager is working on a project. A few months after the project has launched, the project manager starts receiving complaints from business unit managers about the lack of updated project information. What should the project manager do?

A.

Run a Monte Carlo simulation to identify any flaws in the communication matrix

B.

Request that the business unit managers attend weekly review meetings

C.

Check the organizational responsibility of functional managers in the project

D.

Review the communications management plan and stakeholder register

Full Access
Question # 467

A project team is continually being asked by stakeholders to perform rework on their deliverables. The project manager discovers that this is due to poor initial quality. What should the project manager do?

A.

Host a team meeting and ask the team to fix any quality issues immediately since the stakeholders’ needs are the main focus.

B.

Request a subject matter expert (SME) from the project sponsor to identify and address the quality issues with the team.

C.

Facilitate a discussion and come to an agreement about what quality means for both the team and the stakeholders.

D.

Schedule a quality retrospective and discuss the challenges that resulted in poor initial quality with the team.

Full Access
Question # 468

A project manager is working on a large event and developing budgets for sign-off. The stakeholders and project sponsor are all working remotely using various tools to ensure that all documentation is tracked and handled discretely and appropriately. The primary stakeholder has missed several deadlines for the milestone sign-offs, resulting in the project manager being forced to find alternative suppliers for items, now at higher costs. When questioned regarding the delays, the stakeholder says the notifications hadn’t appeared in their email inbox. How should the project manager proceed?

A.

Escalate the issue to the IT department and request they check the software on the stakeholder's computer.

B.

Request human resources (HR) intervene and send the stakeholder to appropriate technical training.

C.

Assess whether the communications channels are appropriate for the primary stakeholder and amend accordingly.

D.

Request the primary stakeholder be replaced to avoid any more delays and budget issues.

Full Access
Question # 469

A project manager has recently been assigned to a construction project. The project has hundreds of stakeholders and three stages. The project manager recognizes that many steps have already been started, including risk identification. The project sponsor asks the project manager to rank the risks contained in the register. How should the project manager respond to the request?

A.

Execute a qualitative analysis to provide identified risks prioritization.

B.

Inform that a quantitative risk prioritization was completed using Monte Carlo simulation.

C.

Inform that a qualitative analysis has already been completed.

D.

Perform a quantitative analysis to provide identified risks prioritization.

Full Access
Question # 470

It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?

A.

Address the required changes in the next release

B.

Review and update the acceptance criteria

C.

Put more emphasis on the definition of done (DoD)

D.

Extend the iterations to complete the items

Full Access
Question # 471

There are several dependent work streams in a project. Some project stakeholders feel that coordination among team members and progress visibility are lacking. What should the project manager do?

A.

Discuss the concerns with the project sponsor

B.

Organize a team meeting to review the project status

C.

Review and update the communications management plan

D.

Escalate the concerns to the project steering committee

Full Access
Question # 472

After a project review meeting, a key stakeholder tells another stakeholder they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation. What should the project manager do?

A.

Request the sponsor ask the key stakeholder to be attentive during the project review meeting

B.

Schedule a meeting with the key stakeholder to address the issue and obtain direct feedback

C.

Email the status report to all stakeholders and ask them to review and provide feedback

D.

Present the status report in a chart and assume everyone understands the report

Full Access
Go to page: