While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves
What should the project manager do?
The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.
What does the project manager need to do first?
A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.
How should the project manager respond’
A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery
Which two actions should the project manager take to mitigate this risk? (Choose two)
A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?
A transportation company is transforming its operational processes and the mam system this company uses to move freight The scope statement is in place An iterative delivery approach has been agreed by all stakeholders. What does the project manager need to do next to help the team understand the work that needs to be done?
During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?
A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again
What should the project lead do next?