Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (PMBOK 7th Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 209

Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.

What should the project manager do to obtain approval of the project budget?

A.

Provide the decision executive with all of the project details and request budget approval from the appropriate person.

B.

Identify the right person with help from local management, present the project summary, and request budget approval.

C.

Approach each of the referred individuals separately and request approval of the project budget from the appropriate person.

D.

Obtain the latest organizational chart and send an email to the appropriate person requesting budget approval.

Full Access
Question # 210

A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?

A.

Communicate the situation to the team and plan for the necessary training and coaching arrangements

B.

Report the situation back to upper management and request to have the scope changed

C.

Plan to hire more experienced team members and lay off a few of the existing team members.

D.

Communicate the situation to the customer and inform them about potential delays in delivery.

Full Access
Question # 211

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

A.

Assessed the technical and organizational readiness for the project and identified risksat the beginning of the first iteration

B.

Requested the product owner's approval to add an external expert to define theacceptance criteria

C.

Defined a clear acceptance criteria at the initiation phase and continued with theproject

D.

Increased the communications between the team member and the product owner

Full Access
Question # 212

A company in the manufacturing industry has started a new initiative to integrate project management and improve product innovation. What first step should the project manager take to increase transparency among the stakeholders?

A.

Define a plan on how communication throughout the project will be handled among the stakeholders.

B.

Set up a project dashboard to show day-to-day project status across the company.

C.

Invite key stakeholders to retrospective and review sessions to receive feedback as often as possible.

D.

Invite upper management to process workshops where current project statuses will be discussed.

Full Access
Question # 213

A project is using a Scrum team from a new vendor to deliver a component. Engaging a new vendor was identified as a delivery risk that, if eventuated, must be escalated to the board. The project manager and product owner work well with the Scrum team, but the vendor misses the first release by a couple of weeks.

What should the project manager do?

A.

Escalate the issue to the board with opportunities to recover the delay as soon as possible.

B.

Work with the product owner and the Scrum team to add 2 weeks to the release schedule.

C.

Work with the product owner and the Scrum team to recover the delay before the last release.

D.

Escalate the issue to the board and plan for the engagement to be terminated.

Full Access
Question # 214

A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager’s project

Which two actions can the project manager take to bring the team back on track? (Choose two)

A.

Establish daily standups to review project progress and track the completion of deliverables

B.

Allow the team members to catch up at their own pace

C.

Alert the business stakeholders immediately of the schedule delay.

D.

Discuss the risk of project delay and work priorities with the respective functional managers

E.

Work with the team to identify options to accelerate project delivery.

Full Access
Question # 215

A company is transitioning from using a predictive approach to using an agile framework on a project. The project sponsor is concerned about the level of uncertainty and how to determine the time and budget required to complete the scope.

What should the project manager do to address this situation?

A.

Communicate to the key stakeholders that the project baseline could not be estimated due to the new framework being used.

B.

Ask the project team to create a high-level budget baseline for the project and provide more detail only for the first project stages.

C.

Review organizational process assets (OPAs) for similar projects to determine the schedule, costs, and resources required to execute them.

D.

Refine the amount of work required for the project with the project team and perform a detailed project baseline accordingly.

Full Access
Question # 216

A project is almost complete when a key stakeholder raises a concern because the functionality of their preferred requirement was not showcased in the prototype. The prototype has already been approved and developers have started work on the final application. What should the project manager do next?

A.

Be firm with the stakeholder, since they would push through any unreasonable requirement

B.

Document the stakeholder's requirements and validate those requirements by engaging stakeholders more often

C.

Inform the stakeholder that little can be done at this time, since core development has begun and the project must be delivered on time

D.

Inform the stakeholder that the requirement will be included in the next deliverable cycle

Full Access
Go to page: