Halloween Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

PMP Exam Dumps - Project Management Professional (2025 Version)

Searching for workable clues to ace the PMI PMP Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s PMP PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 209

A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation

What should the project manager do next?

A.

Document the issue in the issue log and escalate to the project sponsor

B.

Inform the project sponsor and suggest canceling the project

C.

Review the project goals and eat criteria m the project charter

D.

Ask the leader of research and development to decide on next steps

Full Access
Question # 210

A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, lo their knowledge, the project does not seem to have any compliance requirements in their country.

What should the project manager do in this situation?

A.

Request expert advice from the compliance leader to confirm if there are any compliance requirements for the project.

B.

Check with The national compliance agency to determine if the project has any compliance requirements in this country

C.

Trust in the expertise of the sponsor and believe that there are no compliance requirements for this project.

D.

Conduct independent research regarding the data protection policy of the country for legal and regulatory compliance.

Full Access
Question # 211

A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months,

but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities

planned for that date were fulfilled.

How should the project manager inform the stakeholders of the project's progress?

A.

Report that the project has not fulfilled all the expected functionalities.

B.

Complete the outstanding functionalities before informing the sponsor of the project progress.

C.

Communicate the benefit expectations and the action plan for the pending functionalities.

D.

Send an email with the monthly project progress to all relevant stakeholders.

Full Access
Question # 212

A project manager is overseeing a 10-mile piping installation project that was supposed to spend US$15,000 per mile of piping installation and should complete the project exactly 20 weeks from its start. The project manager just found out that only 80% of the work has been completed.

What is the budget at completion (BAC)?

A.

US$100,000

B.

US$150,000

C.

US$300,000

D.

US$250,000

Full Access
Question # 213

A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.

What should the project manager suggest?

A.

Request that all team members receive the newest quality standards training and review one another's work.

B.

Request that a quality specialist be assigned to the project to check the final product at the end of the project.

C.

Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.

D.

Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.

Full Access
Question # 214

Multidisciplinary teams will be needed for a project. The project manager asks the project planner to create a consolidated schedule. The project manager determines from the consolidated schedule that the project's finish date exceeds the requested finish date.

What should the project manager suggest to the planner to analyze this issue?

A.

Verify the total float of each activity of the consolidated project schedule.

B.

Verify the critical path of the consolidated project schedule.

C.

Verify successors and predecessors of each activity of the consolidated project schedule.

D.

Verify the free float of each activity of the consolidated project schedule.

Full Access
Question # 215

A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50 The actual expenditure is US$2,000 and 50 user stories have been delivered.

Which statement is true''

A.

The project is on budget and on schedule.

B.

The project is over budget and behind schedule

C.

The project is under budget and behind schedule.

D.

The project is under budget and on schedule.

Full Access
Question # 216

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid

What should the project manager do?

A.

Add nonpayment to the issue log and keep tracking payments

B.

Hold a meeting with the client to address the issue

C.

Review past projects for payment-related lessons learned

D.

Conduct a meeting with the project team to update the procurement management plan

Full Access
Go to page: