Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-ACP Exam Dumps - PMI Agile Certified Practitioner (PMI-ACP)

Go to page:
Question # 113

How should the project team address this issue?

A.

Suggest pair programming during the retrospective.

B.

Ask the product owner to re-prioritize the user stories at the next retrospective.

C.

Re-estimate the story points with team members at the next iteration planning meeting.

D.

Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.

Full Access
Question # 114

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.

What should the Scrum Master do?

A.

Tell the technical lead to do the testing

B.

Facilitate an open and focused team discussion that reinforces team agreements

C.

Ask the team manager to advise the technical lead that all tasks are important

D.

Encourage the team to take ownership of the delivery

Full Access
Question # 115

An agile team had unexpected technical problems in a project and was not able to complete the deliverables on time. During the retrospective meeting, the team openly discussed the causes for these issues and what can be done to avoid similar situations in the future.

What agile values and principles did the team demonstrate?

A.

The team is being proactive by discussing how to better balance demands and capacity and make sure they have the right competencies.

B.

The team shows respect for one another by listening to everyone's opinions and valuing human interaction during face-to-face meetings.

C.

The team is providing one another with fast feedback to find those responsible for any mistakes so they can be avoided in the future.

D.

The team eliminates potential waste by discussing who should be responsible for future risk management by actively applying the pi an-do-check-act (PDCA) method.

Full Access
Question # 116
A.

Coach team members to improve functional specialties and increase overall velocity.

B.

Identify where team processes misalign with accepted Scrum practices.

C.

Facilitate the identification of problems or issues and help the team resolve them.

D.

Review the backlog to ensure that it is prioritized, refined, and properly tasked.

Full Access
Question # 117

An executive sponsor of a new Scrum team actively attends Scrum ceremonies.

How does this benefit the team?

A.

It helps the team to focus on and meet sprint goals.

B.

It reminds the team about who sponsors the project.

C.

It provides high-level project updates to the sponsor.

D.

It helps to quickly resolve issues using the sponsor's influence.

Full Access
Question # 118

When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?

A.

Calculated planned percent complete (PPC)

B.

Many small minimally marketable features (MMFs)

C.

Story points rather than cost estimates

D.

Calculated earned value (EV)

Full Access
Question # 119

An agile team often fails to deliver its sprint goal. At a sprint retrospective, the more experienced team members complain that the less experienced team members are working too slowly. This creates tension in the team.

What should the scrum master do to remove this tension?

A.

Ask human resources for a training budget so the less experienced team members can increase their skill level and work more efficiently.

B.

Have an individual meeting with the experienced team members and ask them to be more empathic when the less experienced members tail to deliver.

C Remind the team that they are jointly responsible for their deliverables and should consider the different competency levels when agreeing to sprint goals

C.

Initiate a meeting with the team and ask them to decompose the product backlog items further so they become clearer and easier to deliver on time.

Full Access
Question # 120

Midway through a sprint, the Scrum Master identifies that reassigning a certain task could help the team meet its sprint goals.

What should the Scrum Master do next?

A.

Alert the team that sprint goals might not be met and create an alternative plan

B.

Obtain team buy-in to perform modifications to the sprint backlog

C.

Have the sprint proceed as planned

D.

Ask the team to decide if the task should be reassigned

Full Access
Go to page: