Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-ACP Exam Dumps - PMI Agile Certified Practitioner (PMI-ACP)

Go to page:
Question # 65

How should the agile team address this?

A.

Conduct an internal review to validate functionality before shipping

B.

Audit the quality control process to ensure that the product adheres to requirements

C.

Lengthen iterations to ensure there is sufficient time to build functionality

D.

Hold product review sessions with the client to obtain product acceptance

Full Access
Question # 66

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?

A.

Add the new change request as a new user story in the product backlog for the upcoming iteration

B.

Evaluate the impact of the change request and let the team and Product Owner decide and reprioritize based on value

C.

Recommend canceling the current iteration and plan the change request into the next iteration

D.

Recommend that the Product Owner add this change request as a user story to the backlog for the current iteration

Full Access
Question # 67

A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.

What behavior would indicate the team is not working well together?

A.

Team members are sending more emails to the team.

B.

The duration of feedback cycles has increased.

C.

The velocity has increased by having the new team work on items.

D.

New team members requested to move meetings due to time differences.

Full Access
Question # 68

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this. What should the team do next?

A.

Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints

B.

Add risk mitigation time to each requirement

C.

Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation

D.

Hold all risks until they become issues, then add issue resolution tasks to the product backlog

Full Access
Question # 69

A new agile team member notices that the team's current process involves excessive documentation. What should the new team member do?

A.

Teach the team the appropriate agile principle, obtain consensus, and drive adoption.

B.

Allow another team member to prepare those documents that do not appear to bring value.

C.

Notify the project manager about other documentation techniques, and identify which documents bring value and which do not.

D.

Follow the existing process to avoid conflicts.

Full Access
Question # 70

Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched.

How should this situation be handled?

A.

The Agile team should engage stakeholders regarding the proposed designs and ensure that sufficient engagement occurs throughout the project in an adaptive way.

B.

The Agile practitioner should inform the stakeholders that the UI has already been approved by the project team and sponsor, so the team is committed to staying the course.

C.

All stakeholders should go through the approved project charter and business requirements document to reduce the number of late changes or requests.

D.

The stakeholders should contact the project sponsor to get the project halted until new requirements are agreed upon.

Full Access
Question # 71

In a project to develop a supply-and-demand scenario planning tool, the team aims to streamline development and rapidly deliver features. Which approach best supports quick feature delivery while maintaining quality? (Refer to An Excerpt from the Quality Management Plan)

A.

Implementing a systematic approach to automate integration, testing, and deployment activities

B.

Increasing the frequency of stakeholder meetings to gather feedback on feature priorities

C.

Leveraging regular reviews, feedback loops, and lessons learned to adjust at key milestones

D.

Organizing training sessions for end users to ensure effective utilization of the planning tool

Full Access
Question # 72

An agile coach is working with a team that serves clients making product requests by phone. During a daily commitment and replanning meeting, a team member states that they were unable to resolve a client request because they lacked sufficient product knowledge.

What should the agile coach do?

A.

Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.

B.

Ask the line manager to assign the team member with the required technical knowledge.

C.

Meet with the team member's line manager to discuss their development plan.

D.

Provide the team member with training in any lacking areas.

Full Access
Go to page: