Question # 73

Several new stakeholders are concerned about being asked to review a product demo before it is complete. How should the agile coach explain to the stakeholders the value of working this way?

A.

The product owner may act as the stakeholders' proxy at the demo and that the stakeholders do not need to be directly involved with the team.

B.

The demo will show whether or not the team understands the level of effort required to complete the project.

C.

The stakeholders will learn whether or not the implementation has worked by getting immediate feedback so they can correct their assumptions for the next sprint.

D.

The stakeholders will be better positioned to evaluate whether or not the resources expended by the organization are worthwhile.

Full Access
Question # 74

What should the agile team lead do?

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Full Access
Question # 75

What should the project leader do?

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

Full Access
Question # 76

During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.

What is the agile project manager trying to show?

A.

The project's total number of story points.

B.

Product releases and what will be included.

C.

The number of completed user stories.

D.

Where the team is in the project life cycle.

Full Access
Question # 77
A.

Establish a common vision and success criteria and involve all the stakeholders in the iteration reviews.

B.

Invite stakeholders for the iteration reviews but do not include new stakeholders which may limit project success.

C.

Involve all the stakeholders in iteration reviews but do not entertain all expectations of all stakeholders.

D.

Communicate issues to all stakeholders via email and only communicate risks to internal stakeholders.

Full Access
Question # 78

The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.

What should the team do next?

A.

Ask for a team extension so that an engineer with the needed experience can be added to the team.

B.

Suggest that the Product Owner perform the initial investigation and present the outcome to the team.

C.

Request that the Product Owner include a spike in the next iteration's backlog so they can perform an initial investigation.

D.

Propose alternative components with which the team has experience.

Full Access
Question # 79

A Product Owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog.

What should the Product Owner do next?

A.

Remove the second half of the backlog, and communicate their decision in the next backlog grooming meeting

B.

Reprioritize backlog items to future iterations

C.

Work with the team to deploy the first half of the backlog to ensure that value is realized

D.

Meet with project stakeholders to review the backlog and determine if the scope should be adjusted

Full Access
Question # 80

Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?

A.

Raise an impediment that resource tasks will be blocked and notify the Product Owner

B.

Ask the delivery manager for a temporary resource

C.

Ask the Scrum Master to assign that team member's tasks to the next available resource

D.

Assume the team member's tasks to meet iteration goals and notify the Product Owner