Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-ACP Exam Dumps - PMI Agile Certified Practitioner (PMI-ACP)

Go to page:
Question # 89

A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing its teams.

What strategy should be employed to re-organize the teams?

A.

All the teams from both products should be simultaneously called together and allowed to completely self-manage

B.

Teams that worked on similar components in the separate products should be combined to minimize disruption and capitalize on synergies

C.

After grouping individuals by role, multi-discipline teams should be created that are comprised of one member from each role

D.

Features should be prioritized and then teams should be organized around those priorities

Full Access
Question # 90

An agile coach advised a project manager to continuously improve their ability to support their team and remove any obstacles in the project's way. What role is the agile coach advising to the project manager to take on?

A.

Scrum master

B.

People manager

C.

Servant leader

D.

Squad leader

Full Access
Question # 91

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?

A.

Capture risks and make them visible, and use a burndown chart to focus on reducing risks early in the project.

B.

Ask the Scrum Master to extend the sprint's duration to allow more time to work through technical issues.

C.

Place the impacted stories on the story board, and use daily stand-ups to make the product owner aware of the technical issues.

D.

Seek guidance from the development manager.

Full Access
Question # 92

During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories.

What should the Scrum Master do?

A.

Ask the lead developer to identify a solution, and then share the details with the team

B.

Ask a technical manager or architect to determine a solution to the problem

C.

Work with the product owner to add a spike to the next sprint to identify a solution

D.

Create a collaborative team environment so that the team can explore a solution together

Full Access
Question # 93

An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.

What should the team do next?

A.

Run automated tests on the legacy functionality.

B.

Ask the customer to write tests that will be used to know when a story has been correctly developed.

C.

Start coding on the selected user stories to meet the requirements.

D.

Write tests that will be used to know when a story has been correctly developed.

Full Access
Question # 94

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.

What should the product owner do next?

A.

Obtain approval from the change control board to discontinue the component

B.

Ask the team to continue developing the component

C.

Ask the team to discontinue developing the component

D.

Request the sponsor's formal approval to discontinue the component

Full Access
Question # 95

Which agile practice would most significantly increase a team's velocity?

A.

Daily standups

B.

Iteration and release planning

C.

Training in areas of weakness

D.

Iteration

Full Access
Question # 96

Two agile teams from different company sites need to work and collaborate on the same project. What is the first action the agile project manager should take in order to ensure a smooth collaboration between the two teams?

A.

Organize onsite backlog-refinement workshops to ensure common understanding.

B.

Set up weekly meetings where all team members will participate.

C.

Call an onsite meeting where ground rules will be discussed and agreed upon.

D.

Ask the product owner to prepare an onsite team-building activity.

Full Access
Go to page: