Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

PMI-ACP Exam Dumps - PMI Agile Certified Practitioner (PMI-ACP)

Go to page:
Question # 81

A project sponsor suggested a team forgo in-person demonstration meetings and just send the product owner a link to try out the latest increment of working software. The sponsor says this will give the team more time to deliver value.

How should the agile coach explain the importance of an in-person demonstration meeting with the sponsor?

A.

The team needs to see the product owner's body language and facial expressions to understand what they really want.

B.

An in-person meeting helps ensure the product owner will consider their feedback carefully and not ask for any unneeded rework.

C.

It typically takes more time and resources to set up and test a virtual communications tool than to meet in person.

D.

The team will be able to better address the product owner's needs if they can have a conversation and ask questions.

Full Access
Question # 82

Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?

A.

Ensure the teams are working together daily throughout the product development and are keeping the team's progress up to date.

B.

Ensure there is an environment where team members feel comfortable sharing their ideas, concerns, and feedback.

C.

Ensure the customer is provided with regular project status updates and that the meeting minutes are well documented.

D.

Ensure the team is able to release new features and updates frequently so that customers can see the product and provide feedback.

Full Access
Question # 83

A team retrospective was going well until the team lead introduced the "define the next experiment" topic; then the discussion became an argument. A new team member feels strongly that the approach used on their previous team would improve this team's efficiency and effectiveness. The team lead is adamant that they remain with the current approach and the discussion dissolves into a circular argument.

A.

Remind the group that all input is welcome but dissension is not productive and suggest the group move on to another task more agreeable to everyone.

B.

Restate both stances, ask for details of both approaches, and create a chart of similarities and differences.

C.

Construct an Ishikawa diagram for each approach, and use the 5 Whys technique to determine the effectiveness of each approach.

D.

Interject and request this experiment be postponed for 2 months, so the new team member has time to observe the current approach.

Full Access
Question # 84

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

A.

Add a goal to the current iteration to fully mitigate or control the risk.

B.

Balance risk reduction and value adding activities in the next iteration.

C.

Continue with the current plan to maintain team velocity.

D.

Update the risk register and seek direction from a risk specialist.

Full Access
Question # 85

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?

A.

Organize separate meetings with each individual team member.

B.

Create a safe environment for discussions during meetings.C Emphasize rules that need to be respected during meetings

C.

Allow team members to talk when they feel comfortable without any pressure.

Full Access
Question # 86

There is a throughput of 200 tickets in a customer service line. The tickets are raised by employees, with each 8-hour shift averaging 50 tickets in progress.

What is the cycle time to resolve a ticket?

A.

0.25 hour

B.

1 hour

C.

2 hours

D.

4 hours

Full Access
Question # 87

A product roadmap should contain which of these primary components?

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes detailed design plan

D.

Product vision, business objectives, timeframes

Full Access
Question # 88

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns "To do," "In progress," "Ready to be tested," "Test in progress," and "Done." Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of "Ready to be tested" work items has been building up.

What should the team do to improve its speed of delivery?

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns "To do," "In progress," "Ready to be tested," "Test in progress," and "Done." Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of "Ready to be tested" work items has been building up.

What should the team do to improve its speed of delivery?

A.

Analyze the process efficiency, cycle time, and lead time of the entire process.

B.

Estimate in story points and pull in new work per the team's capacity

C.

Add limits to all columns and only pull work in when the queue is not full.

D.

Create a cumulative flow diagram and start looking for bottlenecks.

Full Access
Go to page: