Question # 81

What is an example of a project management office activity that would be most likely undertaken to support a project?

A.

Developing the project management plan.

B.

Developing the business case.

C.

Carrying out A. health check.

D Carrying out day-to-day resource management.

Full Access
Question # 82

The main objective of stakeholder management is to establish stakeholder:

A.

interests.

B.

expectations.

C.

influence.

D.

engagement.

Full Access
Question # 83

Which factor is likely to have the biggest influence over the success of communication?

A.

The size of the communication plan.

B.

The method of communication chosen.

C.

The age range of those communicating.

D.

The type of project being delivered.

Full Access
Question # 84

For successful risk identification to take place what must the project team know as a minimum?

A.

Skills of the team delivering the project.

B.

Project objectives.

C.

Amount of time allowed for risk identification to take place.

D.

Location of the venue Where risk identification Will take place

Full Access
Question # 85

Which of the following best describes a project's context?

A.

The environment in which the business operates.

B.

The geographic location in which the project is undertaken.

C.

The external and internal business environments including stakeholder's interests and influences.

D Industry and business sector practices.

Full Access
Question # 86

The process that evaluates overall project performance to provide confidence is called:

A.

quality assurance.

B.

quality planning.

C.

quality control.

D.

quality audit.

Full Access
Question # 87

What is the main objective of A. RAM?

A.

To provide a clear and concise summary of tasks or deliverables and the specific. responsibilities defined.

B.

To provide an outline of the reporting structure to assist in day-to-day management of the project.

C.

To provide an outline of the scope of the project and the specific deliverables that have been agreed for the project.

D.

To provide an outline of the specific costs of the project and which key deliverables they are allocated to.

Full Access
Question # 88

The primary purpose of a product breakdown structure (PBS) is to:

A.

define all the products that the project will produce.

B.

define precisely what resources will be used on the project.

C.

detail all the products in order of priority.

D.

map out the key project elements identified in the business plan

Full Access