The main aim of quality management is to:
prepare a high-quality management plan.
ensure that deliverables meet appropriate standards.
validate the use of consistent standards.
determine whether to accept change requests.
Which of the following is not an output of a critical path analysis?
Total and free float.
Earliest start time and latest finish time of activities.
Project completion time.
Cost-benefit analysis.
Which one of the following best describes users?
Providers of both strategic and tactical direction to the project.
Those intended to receive benefits or operate outputs.
Facilitators of an appropriate issue resolution procedure.
Those providing full-time commitment to the project.
The business case is owned by the project:
manager.
sponsor.
steering group (board).
senior user.
What are the likely results of building agile working into a or programme?
Reduced schedule time.
increased cost.
Increased efficiency and flexibility.
Reduced risk
What is the main benefit of using prototyping. time boxing or iterative thinking?
They offer tested methods for experimentation and risk reduction
They reduce stakeholders' expectations of how they benefit from the project.
Try allow the project to develop an extended life cycle.
They always deliver the project quicker than planned
Which of the following is the responsibility of a project manager?
Ensuring a project is aligned to the organisation's strategy.
Focusing on project benefits and aligning priorities.
Achieving the project's success criteria.
Improving process, tools and techniques used in a project
When a project has completed the handover and closure phase:
the project deliverables are ready for commissioning.
the project deliverables are ready for handing over to the users.
the project documentation must be disposed of.
the capability is now in place for the benefits to be realised