Question # 49
A.

Cost Breakdown Structure (CBS) shows costs assigned to:

B.

individual work packages using the Work Breakdown Structure (WBS).

C.

individual resources using the Work Breakdown Structure (WBS).

D.

individual resources using the Responsibility Assignment Matrix (RAM).

E.

individual deliverables using the Responsibility Assignment Matrix (RAM)

Full Access
Question # 50

Which one of the following best defines a benefit?

A.

A. positive result of stakeholder management.

B.

The successful management of a project.

C.

An improvement resulting from project deliverables.

D.

The successful delivery of project reports and updates.

Full Access
Question # 51

Which statement best describes a responsibility of the project team members?

A.

To establish formal reporting procedures for project progress.

B.

To assess the progress of their work against the strategic objectives.

C.

To ensure that work assigned to them by the Project Manager is performed.

D.

To identify and resolve project issues affecting the work delegated to them

Full Access
Question # 52

Which one of the following statements BEST defines the purpose of a Product Breakdown Structure(PBS)?

A.

To define the hierarchy of deliverables that are required to be produced on the project

B.

To define how the products are produced by identifying derivations and dependencies

C.

To establish the extent of work required prior to project commissioning and the handover

D.

To identify the health and safety strategies and procedures to be used on the project

Full Access
Question # 53

By carrying out a stakeholder analysis, project managers can assess whether or not stakeholders are:

A.

making unfair judgements.

B.

able to bring expertise to the project team.

C.

in a position to affect their careers.

D.

for or against the project outcomes.

Full Access
Question # 54

A responsibility assignment matrix (RAM) allows the project manager to cross reference:

A.

the work breakdown structure (WBS) with the organisational breakdown structure (OBS) to match resources to the tasks.

B.

the organisational breakdown structure (OBS) with the cost breakdown structure (CBS) to assign A. cost to each resource.

C.

the product breakdown structure (PBS) with the work breakdown structure (WBS) to assign activities to the products.

D.

the organisational breakdown structure (OBS) with the product breakdown structure (PBS) to assign resources to deliverables.

Full Access
Question # 55

What is the agreed reference point that is communicated to stakeholders prior to any work being started?

A.

Verified work breakdown structure.

B.

Deployment baseline.

C.

Configuration record.

D.

Business case.

Full Access
Question # 56

Communication is said to be the means by which information or instructions are:

A.

exchanged.

B.

received.

C.

clarified.

D.

given.

Full Access