Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 33

A business analyst is evaluating solutions against the expected results and logging defects along the way. The next task is to analyze the discrepancies prior to facilitating a go/no-go decision.

Which technique should be used as a starting point to uncover problem areas?

A.

Elicitation

B.

Opportunity analysis

C.

Cost-benefit analysis

D.

Feasibility analysis

Full Access
Question # 34

Which of the following is an input to the Develop Project Charter process?

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

Full Access
Question # 35

Which statement describes the relationship between Manage Quality process and Control process?

A.

Manage Quality is all about following planned processes and provedures for quality, while Control Quality is about making sure that the product which is produced conforms to customer specifications.

B.

Control Quality is all about following planned process and procedures for quality, while Manage Quality is about making sure that the product which is produced conforms to customer specifications.

C.

Manage Quality and Control Quality are the same

D.

Manage Quality is part of Quality Management and Control is a subset of the Stakeholder Management Process group

Full Access
Question # 36

In the basic communication model, which term refers to the method that is used to convey the message?

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Full Access
Question # 37

Which type of managers do composite organizations involve?

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Full Access
Question # 38

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders

Full Access
Question # 39

Which three of the following are the most widely used techniques that a business analyst should implement to gather requirements? (Choose three)

A.

Current state analysis

B.

Facilitated workshops

C.

Scheduled interviews

D.

Shop floor observation

E.

Brainstorming sessions

Full Access
Question # 40

Conflict should be best addressed in which manner?

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Full Access