Question # 73

Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

A.

updates.

B.

defect repairs.

C.

preventive actions.

D.

corrective actions.

Full Access
Question # 74

Which of the following is an output of the Perform Integrated Change Control process?

A.

Cost-benefit analysis

B.

Updated project charter

C.

Approved change request

D.

Multicriteria decision analysis

Full Access
Question # 75

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

A.

Authority

B.

Role

C.

Competency

D.

Responsibility

Full Access
Question # 76

Change request status updates are an output of which process?

A.

Perform Integrated Change Control

B.

Direct and Manage Project Execution

C.

Close Project or Phase

D.

Monitor and Control Project Work

Full Access
Question # 77

Which of the following is the primary output of the Identify Risks process?

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

Full Access
Question # 78

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Full Access
Question # 79

The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

A.

Transfer

B.

Share

C.

Avoid

D.

Accept

Full Access
Question # 80

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

A.

Project document updates

B.

Activity list

C.

Activity attributes

D.

Project calendars

Full Access