Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 9

The process for performing variance analysis may vary, depending on:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

Full Access
Question # 10

After Define Activities and Sequence Activities, the next process is:

A.

Estimate Activity Resources.

B.

Estimate Activity Durations,

C.

Develop Schedule.

D.

Control Schedule.

Full Access
Question # 11

Which statement is true about the project management body of knowledge?

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Full Access
Question # 12

Prototype development may be used as a tool for which of the following risk response strategies?

A.

Avoid

B.

Accept

C.

Mitigate

D.

Exploit

Full Access
Question # 13

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

A.

Expert judgment.

B.

Analytical techniques.

C.

Earned value management.

D.

Group decision-making techniques.

Full Access
Question # 14

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Full Access
Question # 15

Activity cost estimates are quantitative assessments of the probable costs required to:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Full Access
Question # 16

An input to the Collect Requirements process is the:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Full Access
Go to page: