Summer Certification Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: scxmas70

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Searching for workable clues to ace the PMI CAPM Exam? You’re on the right place! ExamCert has realistic, trusted and authentic exam prep tools to help you achieve your desired credential. ExamCert’s CAPM PDF Study Guide, Testing Engine and Exam Dumps follow a reliable exam preparation strategy, providing you the most relevant and updated study material that is crafted in an easy to learn format of questions and answers. ExamCert’s study tools aim at simplifying all complex and confusing concepts of the exam and introduce you to the real exam scenario and practice it with the help of its testing engine and real exam dumps

Go to page:
Question # 9

Which tool is used to develop technical details within the project management plan?

A.

Expert judgment

B.

Project management methodology

C.

Project management information system (PMIS)

D.

Project selection methods

Full Access
Question # 10

What can a requirements traceability matrix enable regardless of the project methodology being used?

A.

Creation of a solid business case

B.

Investigation of the viability of a new product

C.

Identification of missing and superfluous requirements

D.

Evaluation of solution and system performance

Full Access
Question # 11

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

A.

Static payback period = 6 + 1300 / 500 = 6.6

B.

Static payback period = 3 + 1200 / 500 = 5.4

C.

Static payback period = 5 + 700 / 500 = 5.4

D.

Static payback period = 5 + 200 / 500 = 5.4

Full Access
Question # 12

A software project has completed the first iteration, and the testing manager noted that some features were not incorporated and would not approve the software. The business unit manager who will use the software is satisfied with the software and wants to start the rollout.

What should the project manager do?

A.

Escalate the issue to the project management office (PMO).

B.

Organize a meeting between the two managers.

C.

Ask the project team to resolve all of the open issues.

D.

Escalate to the sponsor to decide when to commence the rollout.

Full Access
Question # 13

Which activity involves ensuring that the composition of a projects configuration items is correct?

A.

Configuration Identification

B.

Configuration Status Accounting

C.

Configuration Verification and Audit

D.

Configuration Quality Assurance

Full Access
Question # 14

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

A.

What-if scenario analysis

B.

Simulation

C.

Alternatives analysis

D.

Reserve analysis

Full Access
Question # 15

Which three of the following are key traits of a project leader? (Choose three)

A.

Rely on control.

B.

Focus on near-team goals.

C.

Convey trust and inspire trust in other team members.

D.

Challenge the status quo and do things differently.

E.

Focus on the horizon.

Full Access
Question # 16

An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float.

What is the likelihood the team will complete all 20 story points in the upcoming sprint?

A.

50-75%

B.

25-50%

C.

75-100%

D.

0-25%

Full Access
Go to page: