Summer Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: v4s65

CAPM Exam Dumps - Certified Associate in Project Management (CAPM)

Go to page:
Question # 9

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?

A.

Defining, sequencing, estimating activity duration, and developing a schedule model are so tightly inked that they are viewed as a single process.

B.

The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge

C.

An iterative scheduling and on-demand, pull-based scheduling will be required.

D.

To address the full delivery schedule, a range of techniques may be needed and then need to be adapted

Full Access
Question # 10

In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process'?

A.

Assumption log

B.

Milestone list

C.

Business case

D.

Risk register

Full Access
Question # 11

Match the process with its corresponding process group.

Full Access
Question # 12

What is the purpose of an adaptive standup meeting?

A.

To review what work has been completed, remove impediments, and calculate velocity

B.

To ask the team what work has been completed, calculate velocity, and determine what work will be completed

C.

To ask the team what work has been completed, ask what work will be completed, and report impediments

D.

To update the burndown chart, calculate velocity, and report impediments

Full Access
Question # 13

A program consists of four agile teams. Each team has a separate daily standup. Later each day, there is another standup meeting attended by one member from each team.

Which Scrum technique is this?

A.

Scaled Agile Framework (SAFe®)

B.

Disciplined Agile® (DA™)

C.

Large Scale Scrum (LeSS)

D.

Scrum of Scrums

Full Access
Question # 14

Agile release planning provides a high-level summary timeline of the release schedule based on.

A.

Activities and story points

B.

Iteration and prioritization plans

C.

Product roadmap and the product vision

D.

Tasks and user stories

Full Access
Question # 15

An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.

Which two of the following elements should be included? (Choose two)

A.

Daily scrum

B.

Increments

C.

Sprint retrospective

D.

Sprint backlog

E.

Product backlog

Full Access
Question # 16

When sequencing activities, what does the common acronym FF stand for?

A.

Fixed Fee

B.

Free Float

C.

Fixed Finish

D.

Finish-to-Finish

Full Access
Go to page: